Once a permit is issued, construction must begin within six (6) months. If work does not start, or if work stops for six (6) months or longer, the permit may become inactive and could be revoked.
To keep a permit active, there must be ongoing progress on the project. In most cases, this means passing at least one required inspection within a six-month period. If additional time is needed, a written request for a permit extension may be submitted. Extensions may be approved for up to one (1) year at a time.
Permit Holder Responsibilities
The permit holder is responsible for:
- Requesting inspections at the appropriate stages of construction.
- Providing safe access for inspectors, including ladders, scaffolding, or other equipment if needed.
- Scheduling inspections before work is covered by concrete, drywall, insulation, or other building materials.
- Ensuring all required inspections are completed before requesting a final inspection.
Common Required Inspections
The inspections required for a project depend on the type of work being performed. Common inspections may include:
Footing Inspection
Performed before concrete is poured to verify footing size, depth, and reinforcement.
Foundation Inspection
Performed during foundation construction to verify compliance with approved plans and building code requirements.
Slab or Concrete Preparation Inspection
Performed before concrete is poured to inspect site preparation, reinforcement, and related materials.
Framing Inspection
Performed before walls, ceilings, or floors are covered to inspect structural framing, connectors, and fasteners.
Electrical, Plumbing, and Mechanical Inspections
Performed before wiring, piping, ductwork, or equipment is concealed behind walls, ceilings, or other finishes.
Insulation and Energy Efficiency Inspection
Performed before insulation and energy conservation materials are covered.
Final Inspection
Performed when all permitted work is complete. A final inspection is required before the permit can be closed.
Additional Inspections
Depending on the scope of the project, additional inspections may be required. Your inspector or plan reviewer will let you know if any additional inspections are needed.