This stormwater retrofit project is intended to reconcile competing County objectives to:

  1. incentivize a dense, urban district in downtown Crozet and
  2. provide exceptional protection to downstream drinking water supplies and aquatic resources through a regional stormwater management solution.

The project will mitigate stormwater impacts from existing hardened surfaces and efficiently facilitate future density by providing stormwater management – both water quality and channel/flood protection – for properties with a proposed service district. 

Although water quality management for this area of Crozet is theoretically provided by the Lickinghole Basin, no protection is provided to the approximately 40 miles of streams and other waters located upstream of the Basin (figure on right).  This project addresses this shortcoming by managing runoff from the most densely-developed portion of the Basin’s watershed close to its source.

concept drawing for Downtown Crozet Stormwater Wetlands project

Engineering: Kimley-Horn and Associates, Inc. / Construction: Synchronized Construction Services, Inc. 


 PHOTO LOG

early stage of construction at wetland site (January 26, 2012)
early stage of construction

construction of forebay outfall weir (November 15, 2011)
construction of forebay outfall weir

primary inflow pipes from Jarmans Gap Road (September 27, 2011)
primary inflow pipes from Jarmans Gap Road

roughly excavated wetland cells (April 25, 2012)
roughly excavated wetland cells

installation of rock vane in channel (March 8, 2012)
installation of rock vane in channel

placement of topsoil in wetland cells (September 14, 2012)
placement of topsoil in wetland cells

installation of bridge section over channel (September 7, 2012)
installation of bridge section over channel

channel with early vegetation; a rock vane and bridge can be seen (October 4, 2012)
channel with early vegetation; a rock vane and bridge can be seen in background

wetland cells at final grading prior to seeding (September 24, 2012)
wetland cells at final grading prior to seeding

wetland cells with early plant growth (June 11, 2013)
wetland cells with early plant growth

wetland cells with early plant growth (June 11, 2013)
wetland cells with early growth

wetland cells after season of growth (August 26, 2013)
wetland cells after season of growth