 Progress made in December

  • Completed 2nd Level Steel
  • 80% of roof deck installed
  • Prep for slab on grade (2nd level)
  • Started brick and stone installation


  Anticipated in January
  • Pour slab on grade (2nd level)
  • Masonry on east elevation
  • Complete roof deck 
  • Install parking lot utilities
  • Resolve fiber conflict with storm sewer
  • Coordinate furniture procurement with JMRL