Crozet Square & Oak Street Improvement Project: Construction Progress Update

Post Date:08/29/2025 11:30 AM

As the Crozet Square and Oak Street Improvements Project continues, we are excited to share progress updates and what’s ahead as we move through the remaining stages of the project. This project is part of Albemarle County’s broader vision to create safer, more welcoming public spaces that support a vibrant and accessible community.

Since breaking ground in January, construction has moved steadily through the early stages, with access to all businesses maintained throughout. We’ve seen significant progress, and we’re on track to complete the project by the end of 2025.

We appreciate our community's patience as we work to enhance this important area of downtown Crozet.

Progress So Far

✅ Stage 1 – COMPLETE

  • Improvements to Oak Street; including stormwater upgrades, paving, on street parking spots and sidewalk installation.

✅Stage 2 – COMPLETE

  • Improvements along The Square from Oak Street to the Alley; including stormwater upgrades and a paved path for better access to the Square businesses from Oak Street.

🚧Stage 3 – NEARING COMPLETION

  • Construction improvements on The Square from Crozet Avenue to the Alley; including improvements to the entrance and exit at Crozet Avenue, stormwater upgrades, curb and gutter at the Square parking, upgraded accessible sidewalk along Crozet Avenue and paving and parking space marking.
  • Work also includes removal of sidewalk in front of businesses along The Square and installation of new curb and gutter with accessible sidewalk, stairs, and ramps.
  • Existing utilities will also be upgraded with the installation of new streetlights to replace outdated lighting along the existing sidewalk.

What's Next

🚧 Stage 4 – STARTING SOON (Beginning September 2025)

  • Sidewalk replacement will continue to the eastern side of the Square past the Alley.
  • Improvements will also include grading, paving, and parking space marking of the full length of the Square.

🚧Stage 5 – Beginning Fall 2025

  • Final paving, signage installation, and road striping will be completed, marking the final phase of the project.
  • Construction work on the The Square project is scheduled to be completed by the end of December 2025.

Reminders for Anticipated Traffic Impacts During Construction

This project was designed to be constructed in stages, limiting the impact on businesses and the community while maintaining traffic and access to local businesses. During all construction phases, access to businesses has remained. As we wrap up the project, please keep in mind the following reminders:

  • Intermittent lane closures and detours will continue as each phase progresses.
  • Please follow posted signage, reduce speed in construction zones, and give crews space to work safely.
  • Access to all businesses and private properties along the corridor remains available throughout the construction period.
  • All construction schedules remain weather-dependent and are subject to change. 

Stay tuned for more updates as we approach the final stages, and thank you for helping make Crozet a safer and more vibrant place for all. Visit our website to stay informed about what to expect in terms of traffic impacts and other remaining key project milestones. Still have questions? Email the Facilities & Environmental Services Department.