Allan D. Sumpter                                                                                                                                     Virginia Department of Transportation

Charlottesville Residency Administrator                                                                                                                                     701 VDOT Way

                                                                                                                                                                                  Charlottesville, VA  22911

 

Charlottesville Residency Monthly Report

October 2008

 

 

Albemarle County BOS Action Items

Ken Boyd

Dennis Rooker

Ann Mallek

Sally Thomas

 

 

Preliminary Engineering

Albemarle County

This project has been advertised.  Bids are due on November 26, 2008.

·        Meadow Creek Parkway, U000-104-102 (City portion)

Work is ongoing associated with the Section 106 review that must be done to obtain permit approval from the Corp of Engineers. A minor delay may occur in the advertisement; however, the construction schedule is not expected to be impacted.

·        Route 691 Jarmans Gap Road, 0691-002-158, C501  

VDOT continues work to update plans to reflect field changes in utilities that have occurred due to development since project design began.

A progress meeting was held October 9, 2008.  There was consensus at the meeting to work toward a design that minimizes the impact to adjoining properties and the tree line. A goal has been established to have a public hearing in early 2009.

·        Route 743 Advance Mills Bridge, 0743-002-282 P101, R201, C501, B658 (Permanent Replacement Project) Right-of-way negotiations and utility relocation efforts are ongoing. The project remains on schedule for an early 2009 advertisement.

 

 

Construction                                                                                                       Active Construction Projects

 

(NFO) PM07-002-351, N501 I-64 Pavement Overlay and Guardrail Upgrades

PM-7B-08 Scheduled maintenance asphalt overlay

BRDG-002-796, B672 Rte. 665 Bridge over Buck Mountain Creek superstructure replacement

 

RURAL RUSTIC ROAD UPDATE

ROUTE

ANTICIPATED START DATE

Route 765/668 (Walnut Level Road)

Under construction

Route 722 (Green Mountain Road)

Mid November and progress through the winter with paving in the spring.

 

Planning, Permits and Land Development

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

9

25

Site Plan Reviews for new Subdivisions

13

38

New Entrance Plan Reviews

0

4

Total Permits Processed

78

219

Inspection of new Subdivision Street conducted

18

85

Inspection of new entrance conducted

149

406

Miles of Street Accepted in the State System

0

1.17

 

Traffic Engineering

Completed

 

 

 

RTE

LOCATION

REQUEST

STATUS

 Rts 743/656

 

 Hydraulic & Georgetown

 

 Pedestrian Study

 

Crosswalks & pedestrian signing completed.

 

Being reviewed

 

 

 

RTE

LOCATION

REQUEST

STATUS

Rt 729

Rt 53 to 618

Speed study

Reports finalized; 45 mph speed limit being recommended.  Report in Central Office for review and approval.

Rt  618

Rt 53 to 620

Speed study

Report approved by Central Office. Signs have been ordered, installation will be scheduled once delivered.  

Rt 250

Pantops

Two way left turn lane  (Safety, access and pavement marking review)

Field modifications being drafted

Rt 29

Hollymead to Proffitt

Pavement marking review; request lane shift

Lane striping modifications to be scheduled.

 

Rts 631/743

Rio & Hydraulic

Pedestrian Study

Field modifications being drafted. 

Rts 743/1315

Hydraulic  & Commonwealth

Pedestrian Study

Design modifications complete.  Developing logistics for installation.

Rts 631/1403

Rio & Berkmar

Pedestrian Study

Design modifications complete.  Developing logistics for installation.

Rts 743/667

Hydraulic & Lambs

Pedestrian Study

Design modifications complete.  Developing logistics for installation.

Rt 631

Northfields Rd intersection

Traffic Signal Timing

Under review

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Maintenance work completed

§         Patching operations completed on Routes 617 (Rockfish River), 627 (Warren Ferry/Porters), 684

(Lanetown), 711 (Burton), 712 (Plank), 717 (Secretarys Sand), 726 (James River), 778 (Johnsons),

855 (Faulkner), 1012 (Garden Gate), 1128 (Southern Pkwy), 1129 (Southern Hill Ct), 1202 (St George)

1203 (St George) 

(Dickwoods), 639 (Harrington), 640 (Gilbert Station), 643 (Rio Mills), 668 (Fox Mtn/Fox Ridge),

670 (Damon), 671 (Wesley Chapel), 672 (Via), 683 (Shelton mill), 688 (Midway), 697

(Sutherland), 699 (Boaz), 702 (Reservoir), 704 (Fortune), 711 (Burton), 712 (Coles Rolling), 713

(Glen Dower), 716 (Forsyth), 717 (Old Sand), 718 (Murrays), 719 (Alberene), 721 (Old Dominion),

722 (Old Green Mtn), 725 (Dawsons Mill), 737 (Mountain Vista), 746 (Fosters Branch), 747

(Preddy Creek), 753 (Paces Store/Precinct), 757 (Nelsons), 758 (Smith), 760 (Red Hill School), 767

(Rabbit Valley), 774 (Bear Creek), 782 (Stribling), 785 (Pritchett), 787 (Gillums Ridge), 792 (Stump

Town), 793 (Serene), 826 (Emerys), 856 (Burton)

§         Mowing on Routes 250, 630 (Green Creek), 631 (Appleberry Mtn), 633 (Cove Garden), 655 (Christmas

Hill), 660/661 (Reas Ford), 664 (Frays Mtn), 667 (Catterton), 670 (Damon), 671 (Davis Shop), 680

(Browns Gap Trnpk), 701 (Alberene Church), 704 (Fortune), 711 (Burton), 712 (Coles rolling), 714

(Riding Club), 716 (Forsyth), 717 (Old Sand), 719 (Alberene), 721 (Old Dominion), 726 (James

 River), 731 (Keswick), 734 (Bishop Hill), 737 (Mountain Vista), 755 (Secretarys Sand), 776 (Buck Mtn

Ford), 778 (Johnsons), 792 (Stump Town), 793 (Serene), 795 (James Monroe Pkwy), 811 (Jones Mill),

813 (Starlight), 845 (Totier Creek), 856 (Burton), 1012 (Garden Gate), 1128 (Southern Pkwy), 1129

(Southern Hill Ct), 1301 (Bird), 1302 (Warren), 1303 (Page), 1304 (Harrison), 1309 (Jackson),

1807 (Bishop Ln)

673 (Dickwoods), 689 (Pounding Creek), 1150 (Mill Creek)

(Bleakhouse), 666 (Allen), 690 (Newtown), 692 (Plank), 708 (Dry bridge), 709 (Shadwell), 712

(Plank), 717 (Secretary Sand), 729 (Milton), 743 (Earlysville), 1203 (St George), 1575 (Austin)

§         Trash pickup to include adopt-a highway pickups on Routes on 29, 250, 637 (Dickerson), 654

(Barracks), 660 (Earlysville Forest), 676 (Woodlands), 692 (Plank), 706 (Dudley Mtn), 712 (Plank),

716 (Forsyth)

§         Dust Control on Routes 637 (Dickwoods), 640 (Gilbert Station), 643 (Rio Mills), 674 (Clark), 704

(Fortune), 713 (Glendower), 722 (Old Green Mtn), 725(Dawson Mill), 758 (Smith), 766 (Pea Ridge),

787 (Gillums Ridge).

 

Planned Maintenance work – November 2008

 

 

 

Maintenance Budget

Return to regular agenda