From: Katurah Roell [kroell@ddrva.com]                    ATTACHMENT I
Sent: Monday, May 05, 2008 12:41 PM
To: Judith Wiegand; Wayne Cilimberg
Subject: FW: 00-03-0101P

 

Judy and Wayne, here is a copy of the latest transmittal for the update LOMR It will be reissued within 30 days.  Please provide this information for the Board of Supervisors meeting.

 

Thanks 

 


From: Lori Wade [mailto:LoriWade@mapmodteam.com]
Sent: Tuesday, April 29, 2008 9:48 PM
To: penright@ddrva.com; kroell@ddrva.com
Cc: Sarah Bowen; Lee Brancheau; Lee Brancheau; Jon Janowicz (FEMA)
Subject: 00-03-0101P

Dear Mr. Enright and Mr. Roell,

 

We received the LOMR backup for case 00-03-101P. Our review of the backup date revealed that the topographic work map used for the LOMR contains shows a delineation based on one foot contours, where the revised DFIRMs completed in 2005 used five foot contours. Since no detailed restudy was completed for this flooding source in 2005, and the BFEs are the same (aside from the datum conversion) there does not appear to be a reason why the 5 foot contours were used for mapping in this area.

 

I recommend that we work toward reissuing a LOMR for this area based on the 2000 LOMR's topographic work map. I will get the necessary paperwork and data together and will contact the appropriate community officials for their signature on the proposed revision.

 

If you have any further comments or questions, please feel free to contact me at 609-734-7938 or Sarah Bowen at 215-430-5517.

 

Thank you,

 

Lori Wade

 

Return to exec summary