Charlottesville Residency Monthly Report

February 2008

 

 

Albemarle County BOS Action Items

 

David Slutzky

Ken Boyd

Dennis Rooker

Ann Mallek

Sally Thomas

Lindsay Dorrier

·        Routine Maintenance on Route 713– This need was reported to our Keene Area Headquarters and scheduled.

·        Crosswalk at Cale Elementary School- Installation of a crosswalk at this location is possible. VDOT is in discussions with school officials regarding logistics pertaining to this work.  Assuming an agreement is reached, work will be accomplished this spring.

 

Construction

 

0064-002-2060, SR04; 0064-002-2060, SR04 (Emergency beam end repair to the east and west bound I-64 bridges over Stockton Creek.)

ST-7B-08 (Asphalt surface treatment maintenance schedule)

                                                                                                                        Active Construction Projects

Preliminary Engineering

Albemarle County

·        Route 22 / 250 Intersection Improvements, 0022-002-104, C501

Discussions continue on ways to move the project forward.  These include possible installation by VDOT of traffic control related items such as the signal, signing, pavement markings and guardrail.

Route 631 Meadow Creek Parkway, 0631-002-128, C502, B612, B657                               

Utility relocations have begun on this project while the right-of-way phase continues. Out of 21 total parcels, 15 negotiations are clear, with 3 rights of entry. Of the 6 parcels still pending, two will be cleared within two weeks. Negotiations with City are still ongoing to obtain a right of entry for utility relocations in that area. SWM committee has developed a master planting list for both City and County portions. Roadway landscape plans are under review by County staff. Comments are anticipated back from County by mid-March.

·        Meadow Creek Parkway, U000-104-102 (City portion)

VDOT provided design details to City staff for exhibit being developed for presentation to City

Council as part of SWM design approval process.

·        Route 691 Jarmans Gap Road, 0691-002-158, C501  

VDHR concurred on 10-11-2007 that the project will have an effect on the eligible Crozet Historic District and seven contributing resources; however, the effect on the district will not be adverse. Public Hearing approval is pending. Plans are being developed for R/W submittal. Overall coordination with the Crozet streetscape project has started. This includes SWM and drainage. Meeting with streetscape design consultant to be scheduled for early spring.   

·        Route 656 Georgetown Road, 0656-002-254, C501

A progress meeting was held with County staff to illustrate proposed impacts to affected parcels. County staff is going to investigate acquiring necessary easements to try and accelerate the project. Additional survey for drainage has been ordered and is expected to be done by mid March. County staff is also investigating possible additional existing drainage easements.

·        Route 743 Advance Mills Bridge, 0743-002-282 P101, R201, C501, B658 (Permanent Replacement Project) VDOT is committed to an aggressive design and construction schedule to achieve completion of this project as quickly as possible.  The project will focus on the new bridge, limiting approach work and use of best concurrent engineering practices.  This will allow construction to be completed as early as fall 2009 and no later than spring 2010.

 

 

 

 

 

Planning, Permits and Land Development

 

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

8

78

Site Plan Reviews for new Subdivisions

6

106

New Entrance Plan Reviews

16

101

Total Permits Processed

75

570

Inspection of new Subdivision Street conducted

35

337

Inspection of new entrance conducted

144

944

Miles of Street Accepted in the State System

.94

6.69

 

Traffic Engineering

Albemarle - Completed

 

 

RTE

LOCATION

REQUEST

ACTION

250 (Ivy Rd)

Near intersection with 682

Review of passing zone on Route 250

Sketch complete; passing zone will be closed; to paint crew to schedule work depending on weather & work schedules

Rt 688 (Midway)

Off Miller School Road

Review for speed limit posting on un-posted road

Sketch complete, adding 25 mph advisory speed warning signs 

Rt 250

@ Tilman

Signal study

Not recommending

 

 

 

 

 

 

 

 

 

 

Albemarle – Being reviewed

 

 

RTE

LOCATION

REQUEST

STATUS

Rt 29

Between Polo Grounds & Hollymead

Speed limit review

Speed data indicates that current speed limit is appropriate

Rt 20

Int w/ 712

Operational & safety concerns

Analyzing data; field review pending

Rt 729

Rt 53 to 618

Speed study

TE reviewing; analyzing data & compiling report

Rt  618

Rt 53 to 620

Speed study

TE reviewing; analyzing data & compiling report

Rt 805

@ 601

Safety review

TE reviewing; analyzing data

Rt 250

Pantops

Two way left turn lane  (Safety, access and pavement marking review)

TE reviewing

Rt 29

Hollymead to Proffitt

Pavement marking review; request lane shift

TE reviewing

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Maintenance work completed

Patching operations completed on Routes 620 (Rolling), 1170 (Signal Hill) and 1171 (Beacon Hill)

(Green Creek), 633 (Cove Garden), 637 (Dickwoods), 643 (Rio Mills), 646 (Lovers Ln), 672

(Blufton), 673 (Slam Gate), 678 (Decca Ln), 682 (Gilliums Ridge), 688 (Midway), 689

(Pounding Creek), 699 (Boaz), 713 (Glendower), 712 (Coles Rolling), 722 (Old Green Mtn), 724

(Lewiston Ford), 735 (Mount Alto), 737 (Mountain Vista), 766 (Pea Ridge), 784 (Burnt Mill),

824 (Patterson Mill)

§         Mowing on Routes 53, 719 (Alberene), 722 (Old Green Mtn)

§         Cleared pipes and ditch work on Routes 630 (Green Creek), 640 (Turkey Sag), 722 (Old Green Mtn),

736 (White Mtn),

611(Jarmans Gap), 614 (Sugar Hollow), 616 (Black Cat), 618 (Martin Kings), 625 (Hatton Ferry),

627 (Porters), 630 (Green Creek), 635 (Craigs Store), 636 (Batesville), 637 (Dickwoods), 640

(Gilbert Station), 641 (Burnley Station), 657 (Lambs), 665 (Buck), 676 (Owensville), 684

(Half Mile Branch), 689 (Pounding Creek), 692 (Plank), 694 (Miller Lake), 708 (Secretarys), 712

(Coles Rolling), 721 (Old Dominion), 725 (Dawsons Mill), 728 (Ed Jones), 729 (Buck Island), 759

(Three Chopt), 1439 (Westmoreland), 1721 (Timberwood Blvd)

 

Planned Maintenance work – March  2008

 

Rural Rustic Road Update

 

The only remaining rural rustic road project carried over into the 2008 calendar year is Rt 647, Maxfield Road.  Below is the current status.

 

Rte 647 (Maxfield Road)

 

Maintenance Budget

Return to regular agenda