SUMMARY CAPITAL COST ESTIMATE          
Eastern Connector Study Alternative Alignments        
September 8, 2008          
         
Alternatives/Alignment Options Total Estimated Construction Cost Public Lands Estimated Right-of-Way Cost Private Lands Estimated Right-of-Way Cost Total Estimated Right-of-Way Cost Total Estimated Alternative Cost
           
Alt. 1 - Proffit Road Relocated  $               38,000,000  $                              -  $               26,000,000  $               26,000,000  $               64,000,000
           
Alt. 2 - Polo Grounds Road          
Alignment 1  $               49,000,000  $                              -  $               17,000,000  $               17,000,000  $               66,000,000
Alignment 2  $               72,000,000  $                              -  $               22,000,000  $               22,000,000  $               94,000,000
           
Alt. 3 - Rio Road to Route 20          
Two-lane Roadway          
3 - Through Center of Pen Park  $               25,000,000  $                 4,000,000  $               46,000,000  $               50,000,000  $               75,000,000
3A - North side of Pen Park  $               50,000,000  $                 1,000,000  $               16,000,000  $               17,000,000  $               67,000,000
3B - South side of Pen Park Option #1  $               29,000,000  $                 5,000,000  $                 6,000,000  $               11,000,000  $               40,000,000
           
Four-lane Roadway          
3 - Through Center of Pen Park  $               49,000,000  $                 7,000,000  $               61,000,000  $               68,000,000  $             117,000,000
3A - North side of Pen Park  $             115,000,000  $                 2,000,000  $               52,000,000  $               54,000,000  $             169,000,000
3B - South side of Pen Park Option #1  $               68,000,000  $                 6,000,000  $               17,000,000  $               23,000,000  $               91,000,000
3C - South side Option #2  $               66,000,000  $                 8,000,000  $               14,000,000  $               22,000,000  $               88,000,000
3D - Modified center alignment  $               50,000,000  $                 8,000,000  $               53,000,000  $               61,000,000  $             111,000,000
           
         
Note: All costs shown are rounded to the nearest $1.0 million and are in Year 2008 dollars      

 