| SUMMARY CAPITAL COST ESTIMATE | |||||
| Eastern Connector Study Alternative Alignments | |||||
| September 8, 2008 | |||||
| Alternatives/Alignment Options | Total Estimated Construction Cost | Public Lands Estimated Right-of-Way Cost | Private Lands Estimated Right-of-Way Cost | Total Estimated Right-of-Way Cost | Total Estimated Alternative Cost |
| Alt. 1 - Proffit Road Relocated | $ 38,000,000 | $ - | $ 26,000,000 | $ 26,000,000 | $ 64,000,000 |
| Alt. 2 - Polo Grounds Road | |||||
| Alignment 1 | $ 49,000,000 | $ - | $ 17,000,000 | $ 17,000,000 | $ 66,000,000 |
| Alignment 2 | $ 72,000,000 | $ - | $ 22,000,000 | $ 22,000,000 | $ 94,000,000 |
| Alt. 3 - Rio Road to Route 20 | |||||
| Two-lane Roadway | |||||
| 3 - Through Center of Pen Park | $ 25,000,000 | $ 4,000,000 | $ 46,000,000 | $ 50,000,000 | $ 75,000,000 |
| 3A - North side of Pen Park | $ 50,000,000 | $ 1,000,000 | $ 16,000,000 | $ 17,000,000 | $ 67,000,000 |
| 3B - South side of Pen Park Option #1 | $ 29,000,000 | $ 5,000,000 | $ 6,000,000 | $ 11,000,000 | $ 40,000,000 |
| Four-lane Roadway | |||||
| 3 - Through Center of Pen Park | $ 49,000,000 | $ 7,000,000 | $ 61,000,000 | $ 68,000,000 | $ 117,000,000 |
| 3A - North side of Pen Park | $ 115,000,000 | $ 2,000,000 | $ 52,000,000 | $ 54,000,000 | $ 169,000,000 |
| 3B - South side of Pen Park Option #1 | $ 68,000,000 | $ 6,000,000 | $ 17,000,000 | $ 23,000,000 | $ 91,000,000 |
| 3C - South side Option #2 | $ 66,000,000 | $ 8,000,000 | $ 14,000,000 | $ 22,000,000 | $ 88,000,000 |
| 3D - Modified center alignment | $ 50,000,000 | $ 8,000,000 | $ 53,000,000 | $ 61,000,000 | $ 111,000,000 |
| Note: All costs shown are rounded to the nearest $1.0 million and are in Year 2008 dollars | |||||