March 7, 2008

 

Scott Collins

Collins Engineering

800 East Jefferson Street, Suite 300

Charlottesville, VA 22902

 

 

RE:      PROJECT: SP 2005-00028 / Biscuit Run #2 (Mid) Sign # 3, 6, and 22.

TAX MAP/PARCEL: 90-5, 90-6D

 

AND

 

            PROJECT: SP 2006-00001 / Biscuit Run #3 (Southern) - Sign # 3, 6, and 22

TAX MAP/PARCEL: 90-6D

 

AND

 

PROJECT: SP 2006-00002 / Biscuit Run Stream Crossing #1 (Northern) - Sign # 3, 6, and 22

            TAX MAP/PARCEL: 90-A-3 and 90-A1-1

 

Dear Mr. Collins:

 

The Albemarle County Planning Commission, at its meeting on February 26, 2008, recommended approval of the above-noted petition to the Board of Supervisors.

 

Please note that this approval is subject to the following conditions:

 

Action on SP-2005-28 Biscuit Run Stream Crossing (Middle):

1.    The applicant must obtain a map revision, letter of revision, or letter of amendment as required from the Federal Emergency Management Agency (FEMA) and copy the County Engineer on all correspondence.

2.       Army Corp of Engineers, Virginia Department of Environmental Quality, and other necessary state and federal agency approvals must be obtained prior to issuance of grading permits for construction of the new stream crossing and approaches.

3.       County approval of road and bridge plans for the crossing to be in accord with the application plan, as determined by the County Engineer.

4.       County approval of a grading and an erosion and sediment control plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

5.       County approval of a stream buffer mitigation plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

6.       Grading within floodplain shall be confined to the minimum necessary to construct the bridge.  Changes in final design of the bridge, such as use of a longer span, are acceptable if the changes reduce impacts to the floodplain, in the opinion of the County Engineer.

7.       Construction of the new crossing shall commence on or before April 9, 2013, or this special use permit shall be deemed abandoned and the authority granted hereunder shall thereupon terminate.

8.       VDOT approval shall be required for the stream crossing to ensure that the roads and the bridges meet VDOT standards. 

9.       The approval of this special use permit does not supersede or modify any proffer or provision of the Code of Development related to ZMA-2005-00017 or any subsequent amendments thereto.

 

The motion passed by a vote of 6:0. 

 

View staff report and attachments

View PC minutes

Return to regular agenda

 

Action on SP-2006-00001 Biscuit Run Stream Crossing (Southern):

1.    The applicant must obtain a map revision, letter of revision, or letter of amendment as required from the Federal Emergency Management Agency (FEMA) and copy the County Engineer on all correspondence.

2.       Army Corp of Engineers, Virginia Department of Environmental Quality, and other necessary state and federal agency approvals must be obtained prior to issuance of grading permits for construction of the new stream crossing and approaches.

3.       County approval of road and bridge plans for the crossing to be in accord with the application plan, as determined by the County Engineer.

4.       County approval of a grading and an erosion and sediment control plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

5.       County approval of a stream buffer mitigation plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

6.       Grading within floodplain shall be confined to the minimum necessary to construct the bridge.  Changes in final design of the bridge, such as use of a longer span, are acceptable if the changes reduce impacts to the floodplain, in the opinion of the County Engineer.

7.       Construction of the new crossing shall commence on or before April 9, 2013, or this special use permit shall be deemed abandoned and the authority granted hereunder shall thereupon terminate.

8.       VDOT approval shall be required for the stream crossing to ensure that the roads and the bridges meet VDOT standards. 

9.       The approval of this special use permit does not supersede or modify any proffer or provision of the Code of Development related to ZMA-2005-00017 or any subsequent amendments thereto.

 

The motion passed by a vote of 6:0. 

 

Action on SP-2006-00002 Biscuit Run Stream Crossing (Northern):

1.    The applicant must obtain a map revision, letter of revision, or letter of amendment as required from the Federal Emergency Management Agency (FEMA) and copy the County Engineer on all correspondence.

2.       Army Corp of Engineers, Virginia Department of Environmental Quality, and other necessary state and federal agency approvals must be obtained prior to issuance of grading permits for construction of the new stream crossing and approaches.

3.       County approval of road and bridge plans for the crossing to be in accord with the application plan, as determined by the County Engineer.

4.       County approval of a grading and an erosion and sediment control plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

5.       County approval of a stream buffer mitigation plan prior to the issuance of a grading permit for construction of the new stream crossing and approaches.

6.       Grading within floodplain shall be confined to the minimum necessary to construct the bridge.  Changes in final design of the bridge, such as use of a longer span, are acceptable if the changes reduce impacts to the floodplain, in the opinion of the County Engineer.

7.       Construction of the new crossing shall commence on or before April 9, 2013, or this special use permit shall be deemed abandoned and the authority granted hereunder shall thereupon terminate.

8.       VDOT approval shall be required for the stream crossing to ensure that the roads and the bridges meet VDOT standards. 

9.       The approval of this special use permit does not supersede or modify any proffer or provision of the Code of Development related to ZMA-2005-00017 or any subsequent amendments thereto.

 

The motion passed by a vote of 6:0. 

 

Please be advised that the Albemarle County Board of Supervisors will review this petition and receive public comment at their meeting on April 9, 2008.

 

If you should have any questions or comments regarding the above noted action, please do not hesitate to contact me at (434) 296-5832.

 

Sincerely,

 

 

 

Tamara Ambler

Natural Resources Manager