Charlottesville Residency Monthly Report

December 2007

 

 

Albemarle County BOS Action Items

 

David Slutzky

Ken Boyd

Dennis Rooker

Ann Mallek

 

Construction

 

All active construction projects for the 2007 season have been substantially completed.

                                                                                                                        Active Construction Projects

Preliminary Engineering

Albemarle County

Right of way is near completion and utilities have been relocated.  VDOT, Albemarle County and Luck Stone are continuing to work towards construction starting in the spring of 2008.

The right-of-way phase continues on this project.  Out of 21 total parcels, 10 negotiations are complete, 1 right of entry has been acquired and 10 parcels are still pending.  It is expected that a right of entry for the CATEC property will be acquired by January 7th.  The right-of-way revision for the City has been completed and an offer is ready to be made pending the City Attorney and Attorney General’s Office discussions. 

Progress continues related to revised storm water design including contouring and plantings.

VDHR concurred on 10-11-2007 that the project will have an effect on the eligible Crozet Historic District and seven contributing resources; however, the effect on the district will not be adverse. Public Hearing approval is pending.

All survey is completed and design work related to cross sections and drainage continues.  A progress meeting will be tentatively planned for January.

Survey work is completed and preliminary design has begun.

A meeting was held with the Consulting Parties to discuss potential impacts to the historic district and mitigation alternatives.  The next step will be for VDOT Environmental staff to begin work on the necessary federal environmental documents.

The monthly update to the rural rustic program is attached to this report

 

Planning, Permits and Land Development

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

16

54

Site Plan Reviews for new Subdivisions

5

85

New Entrance Plan Reviews

14

71

Total Permits Processed

85

431

Utility Permits Processed

25

89

Inspection of new Subdivision Street conducted

48

245

Inspection of new entrance conducted

122

638

Miles of Street Accepted in the State System

.66

3.28

 

Traffic Engineering

Albemarle - Completed

 

 

RTE

LOCATION

REQUEST

ACTION

 Rt 29

@ post office entrance

Safety review for entrance

Field review complete; removal of curb to extend thru & right turn lanes

Rt 631 (Rio)/Waldorf School/Pen Park

Intersection

Being reviewed for cross walk and pedestrian crossing

Not recommending cross walk & pedestrian crossing at this time until sidewalk or trail installed

250 (Ivy Rd)

Near intersection with 682

Review of passing zone on Route 250

Sketch complete; passing zone will be closed; to paint crew to schedule work depending on weather & work schedules

Rt 688 (Midway)

Off Miller School Road

Review for speed limit posting on un-posted road

Sketch complete, adding 25 mph advisory speed warning signs 

 

 

 

 

 

 

 

 

 

 

 

 

Albemarle – Being reviewed

 

 

RTE

LOCATION

REQUEST

STATUS

250 (Richmond Rd)

I-64 interchange to High/River Rd intersection in Charlottesville

Coordinate signals on this corridor

Project in design & planned development stages.  Met with City to include signal at Rt 250/High Street.  Additional counts complete and being analyzed.

 Rt 29

Between Polo Grounds & Hollymead

Speed limit review

Analyzing data; need field review and speed data

Rt 20

Int w/ 712

Operational & safety concerns

Analyzing data

Rt 250

@ Glenmore

Traffic signal study

TE reviewing; count completed; analyzing data

Rt 729

Rt 53 to 618

Speed study

TE reviewing; gathering data

T 618

Rt 53 to 620

Speed study

TE reviewing; gathering data

Rt 250

@ Tilman

Signal study

TE reviewing

Rt 805

@ 601

Safety review

TE reviewing

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Maintenance work completed

Albemarle County

(Albevanna Springs), 627 (Porters/Carters Mtn), 643 (Polo Grounds), 648 (Clarks Tract), 649 (Proffitt),

656 (Georgetown), 657 (Lambs), 680 (Browns Gap), 708 (Taylors Gap/Red Hill), 723

(Sharon/Chestnut Grove), 745 (Arrowhead valley), 791 (Wyant Ln), 1528 (Derby ln)

636 (Batesville), 637 (Dickwoods), 640 (Turkey Sag), 643 (Rio Mills), 662 (Bleakhouse), 667

(Catterton), 668 (Fox Mtn), 671 (Wesley Chapel), 674 (Clark), 673 (Slam Gate), 678 (Fox Ridge),

683 (Shelton Mill), 685 (Bunker Hill), 687 (Shiffletts Mill), 688 (Midway), 691

(Jarmans Gap), 702 (Reservoir), 713 (Glendower), 721 (Old Dominion), 731 (Keswick), 736 (White Mtn),

737 (Mountain Vista), 746 (Fosters Branch), 762 (Rose Hill Church Ln), 769 (Rocky Hollow), 783

(Millwood), 784 (Burnt Mill), 795 (Blenheim), 807 (Hawkshill), 824 (Patterson Mill),

825 (Yancey Mill Ln).

627 (Carters Mtn), 633 (Heards Mtn), 640 (Turkey Sag), 645 (Wildon Grove), 646 (Lovers Ln),

656 (Georgetown), 684 (Half Mile Branch), 691 (Castle Rock), 710 (Taylors Gap), 839

(whippoorwill), 854 (Carrsbrook), 1446 (George Rogers)

(Jarmans Gap), 616 (Black Cat), 633 (Heards Mtn), 634 (Spring Valley), 637 (Dickwoods), 640

(Turkey Sag), 645 (Magnolia), 646 (Lovers Ln), 680 (Browns Gap), 689 (Pounding Creek), 692

(Plank), 702 (Reservoir), 803 (Goodloe), 1320 (Terrell).

 

Planned Maintenance work – January  2008

 

Advance Mills Temporary Bridge update

 

VDOT will be using what is known within the Department as a Special Advertisement and Award Process (SAAP).  Accounting for typical procedures, the expected timeline for this project in accordance with VDOT’s Advertisement and Letting Calendar is as follows:

 

·        Final Contract Assembly submitted to VDOT’s Central Office by late December, 2007

·        Advertisement for Bids: January 22, 2008

·        Bids Received: February 27, 2008

·        Award of Contract: mid-March

·        Expected Begin Construction: early April

·        Construction completion expected within 4-6 weeks

 

Our staff has a high level of confidence in this timeline provided no substantial issues develop regarding our coordination with DHR and reasonable bids are received.

 

Maintenance Budget

1/2/2008

 

Rural Rustic Program 2007

Albemarle County

 

 

Rte 647 (Maxfield Road)

 

 

 

Projects Completed

 

 