All active construction projects for the 2007 season have been substantially completed.
Right of way is near completion and utilities have been relocated. VDOT, Albemarle County and Luck Stone are continuing to work towards construction starting in the spring of 2008.
The right-of-way phase continues on this project. Out of 21 total parcels, 10 negotiations are complete, 1 right of entry has been acquired and 10 parcels are still pending. It is expected that a right of entry for the CATEC property will be acquired by January 7th. The right-of-way revision for the City has been completed and an offer is ready to be made pending the City Attorney and Attorney General’s Office discussions.
Progress continues related to revised storm water design including contouring and plantings.
VDHR concurred on 10-11-2007 that the project will have an effect on the eligible Crozet Historic District and seven contributing resources; however, the effect on the district will not be adverse. Public Hearing approval is pending.
All survey is completed and design work related to cross sections and drainage continues. A progress meeting will be tentatively planned for January.
Survey work is completed and preliminary design has begun.
A meeting was held with the Consulting Parties to discuss potential impacts to the historic district and mitigation alternatives. The next step will be for VDOT Environmental staff to begin work on the necessary federal environmental documents.
The monthly update to the rural rustic program is attached to this report
|
Land Development Items |
Total This Month |
Total This Fiscal Year |
|
Special Use Permits and Rezoning Application Review |
16 |
54 |
|
Site Plan Reviews for new Subdivisions |
5 |
85 |
|
New Entrance Plan Reviews |
14 |
71 |
|
Total Permits Processed |
85 |
431 |
|
Utility Permits Processed |
25 |
89 |
|
Inspection of new Subdivision Street conducted |
48 |
245 |
|
Inspection of new entrance conducted |
122 |
638 |
|
Miles of Street Accepted in the State System |
.66 |
3.28 |
|
Albemarle - Completed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
ACTION |
|
Rt 29 |
@ post office entrance |
Safety review for entrance |
Field review complete; removal of curb to extend thru & right turn lanes |
|
Rt 631 (Rio)/Waldorf School/Pen Park |
Intersection |
Being reviewed for cross walk and pedestrian crossing |
Not recommending cross walk & pedestrian crossing at this time until sidewalk or trail installed |
|
250 (Ivy Rd) |
Near intersection with 682 |
Review of passing zone on Route 250 |
Sketch complete; passing zone will be closed; to paint crew to schedule work depending on weather & work schedules |
|
Rt 688 (Midway) |
Off Miller School Road |
Review for speed limit posting on un-posted road |
Sketch complete, adding 25 mph advisory speed warning signs |
|
Albemarle – Being reviewed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
STATUS |
|
250 (Richmond Rd) |
I-64 interchange to High/River Rd intersection in Charlottesville |
Coordinate signals on this corridor |
Project in design & planned development stages. Met with City to include signal at Rt 250/High Street. Additional counts complete and being analyzed. |
|
Rt 29 |
Between Polo Grounds & Hollymead |
Speed limit review |
Analyzing data; need field review and speed data |
|
Rt 20 |
Int w/ 712 |
Operational & safety concerns |
Analyzing data |
|
Rt 250 |
@ Glenmore |
Traffic signal study |
TE reviewing; count completed; analyzing data |
|
Rt 729 |
Rt 53 to 618 |
Speed study |
TE reviewing; gathering data |
|
T 618 |
Rt 53 to 620 |
Speed study |
TE reviewing; gathering data |
|
Rt 250 |
@ Tilman |
Signal study |
TE reviewing |
|
Rt 805 |
@ 601 |
Safety review |
TE reviewing |
(Albevanna Springs), 627 (Porters/Carters Mtn), 643 (Polo Grounds), 648 (Clarks Tract), 649 (Proffitt),
656 (Georgetown), 657 (Lambs), 680 (Browns Gap), 708 (Taylors Gap/Red Hill), 723
(Sharon/Chestnut Grove), 745 (Arrowhead valley), 791 (Wyant Ln), 1528 (Derby ln)
636 (Batesville), 637 (Dickwoods), 640 (Turkey Sag), 643 (Rio Mills), 662 (Bleakhouse), 667
(Catterton), 668 (Fox Mtn), 671 (Wesley Chapel), 674 (Clark), 673 (Slam Gate), 678 (Fox Ridge),
683 (Shelton Mill), 685 (Bunker Hill), 687 (Shiffletts Mill), 688 (Midway), 691
(Jarmans Gap), 702 (Reservoir), 713 (Glendower), 721 (Old Dominion), 731 (Keswick), 736 (White Mtn),
737 (Mountain Vista), 746 (Fosters Branch), 762 (Rose Hill Church Ln), 769 (Rocky Hollow), 783
(Millwood), 784 (Burnt Mill), 795 (Blenheim), 807 (Hawkshill), 824 (Patterson Mill),
825 (Yancey Mill Ln).
627 (Carters Mtn), 633 (Heards Mtn), 640 (Turkey Sag), 645 (Wildon Grove), 646 (Lovers Ln),
656 (Georgetown), 684 (Half Mile Branch), 691 (Castle Rock), 710 (Taylors Gap), 839
(whippoorwill), 854 (Carrsbrook), 1446 (George Rogers)
(Jarmans Gap), 616 (Black Cat), 633 (Heards Mtn), 634 (Spring Valley), 637 (Dickwoods), 640
(Turkey Sag), 645 (Magnolia), 646 (Lovers Ln), 680 (Browns Gap), 689 (Pounding Creek), 692
(Plank), 702 (Reservoir), 803 (Goodloe), 1320 (Terrell).
VDOT will be using what is known within the Department as a Special Advertisement and Award Process (SAAP). Accounting for typical procedures, the expected timeline for this project in accordance with VDOT’s Advertisement and Letting Calendar is as follows:
· Final Contract Assembly submitted to VDOT’s Central Office by late December, 2007
· Advertisement for Bids: January 22, 2008
· Bids Received: February 27, 2008
· Award of Contract: mid-March
· Expected Begin Construction: early April
· Construction completion expected within 4-6 weeks
Our staff has a high level of confidence in this timeline provided no substantial issues develop regarding our coordination with DHR and reasonable bids are received.

1/2/2008
Rural Rustic Program 2007
Albemarle County
Rte 647 (Maxfield Road)
Projects Completed