Slurry paving operations on Rte. 250 from the Albemarle Co. line to Rte. 731 are complete. A portion of permanent pavement marking remains to complete project.
Paving, pavement marking and shoulder stone placement is completed at the following areas: East and westbound lanes Route 33 in Greene Co. from Route 1103 to Route 633
Rte. 810 in Greene Co. from the Albemarle Co line to Rte. 631.
Rte. 250 from Rte. 151 to end of two lane section at the I-64 interchange.
Project No. ST-7B-07 (Asphalt surface treatment schedule)
Completed this month.
R/W is currently being negotiated. VDOT, Albemarle County and Luck Stone are scheduled to meet on July 20, 2007 to follow up discussions on the construction funding for this project.
This project is fully funded. The R/W phase continues with appraisals and negotiations ongoing. Target date for right of way to be cleared remains November 2007. Utility relocations will begin afterwards. This project remains on schedule for a June 2008 advertisement.
Project funding update: Estimated funding shortfall at this time is $5.1 million. Potential cost reductions and additional funding have been identified for $3.9 million leaving total shortfall at $1.2 million
County and residency staffs will soon be meeting to discuss funding options based upon projected state funding and revenue sharing allocations. District Design Staff continues work on plan updates based upon recent development impacts along this roadway. Once these updates and funding questions are resolved, a target advertisement date will be set.
Basic Survey information has been plotted and work is underway to expand it to greater detail. Design staff is reviewing information provided by the county to clarify certain areas where there are questions regarding easements and right-of-ways. A meeting to update the scope of the project is expected in late July or early August.
Aerial survey is completed and follow up work is underway by ground survey crews to complete the survey.
The monthly update to the rural rustic program is attached to this report.
|
Land Development Items |
Total This Month |
Total This Fiscal Year |
|
Special Use Permits and Rezoning Application Review |
5 |
51 |
|
Site Plan Reviews for new Subdivisions |
21 |
147 |
|
New Entrance Plan Reviews |
10 |
158 |
|
Total Permits Processed |
85 |
916 |
|
Utility Permits Processed |
7 |
139 |
|
Inspection of new Subdivision Street conducted |
38 |
156 |
|
Inspection of new entrance conducted |
150 |
1302 |
|
Miles of Street Accepted in the State System |
.90 |
5.95 |
|
Albemarle - Completed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
ACTION |
|
29 (Seminole Trail) |
Int with Towne Center Drive & Holly Memorial Cemetery |
Signal not functioning properly |
Repaired video detection processor in signal controller |
|
616 (Black Cat Rd) |
Int with 759 (Three Chopt Rd) |
Traffic turning left from 616 to 759 not yielding to oncoming on 616 |
Installed “left turning vehicles yield to oncoming traffic” sign |
|
631 (Rio Road) |
Old Albemarle Christian Academy |
Remove “children crossing” sign |
Sign removed due to academy closing |
|
250 (Ivy Rd) |
Intersection w/ SB 29 exit ramp & Canterbury/Old Garth |
Repair signal vehicle detection |
Video detection units installed at both locations |
|
640 (Gilbert Station Rd) |
Just south of Five Forks Lane |
24 Hr traffic count (speed & classification) |
Data collected, compiled and submitted to the residency for post rural rustic road evaluation |
|
250 (Ivy Rd) |
Between 637 (Dick Woods Rd) & 1630 (Rodes Dr) |
Install two way left turn lane |
In conjunction with pavement overlay, approximately 600’ of two way left turn lane was added at this location |
|
Albemarle – Being reviewed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
STATUS |
|
53 |
Section of route east and west of entrance to Monticello |
Safety and operational review |
TE has performed preliminary field review and proceeding with detailed analysis |
|
1521 (Powell Cr Dr) |
Section of route where traffic calming measures installed |
Perform follow up evaluation of the effectiveness of the traffic calming measures |
TE requested to perform speed study |
|
1090 (Lego Drive) |
Entire route |
Traffic calming |
Preliminary design modified at the request of County Staff and presented to Ashcroft community |
|
250 (Ivy Rd) |
Near intersection with 682 |
Review of passing zone on Route 250 |
TE reviewing |
|
250 (Richmond Rd) |
I-64 interchange to High/River Rd intersection in Charlottesville |
Coordinate signals on this corridor |
Project in preliminary stages of scoping and design |
614 (Garth), 618 (Jefferson Mill), 621 (Wolftrap), 625 (Hatton Ferry), 626 (James River), 633
(Cove Garden), 641 (Burnley Station), 644 (Burnley) 658 (Barracks Farm), 684
(Lanetown/Half Mile Branch), 708 (Red Hill/Secretarys), 712 (Plank), 717 (Secretarys Sand),
737 (Mtn Vista), 747 (Preddy Creek), 784 (Doctors Xing), 810 (Crozet/White Hall), 820
(Buckingham Cir), 824 (Patterson Mill), 829 (Horseshoe Bend), and 1302 (Hardware Hills).
(Porters/Carters Mtn), 629 (Browns Gap), 633 (Cove Garden), 640 (Gilbert Station), 641
(Burnley Station), 643 (Rio Mills), 646 (Lovers Ln), 661 (Reas Ford Ln), 662 (Bleakhouse), 667
(Catterton), 668 (Fox Mtn), 671 (Ballards Mill/Davis Shop), 672 (Via), 673 (Slam Gate), 674
(Clark), 678 (Ridge), 683 (Shelton Mill), 684 (Lanetown), 687 (Shiffletts Mill), 694
(Miller Lake), 697 (Sutherland), 699 (Boaz), 702 (Reservoir), 703 (Pocket Ln), 704 (Fortune Ln),
711 (Burton), 712 (Coles Rolling), 713 (Dyers Mill), 714 (Riding Club), 717
(Secretarys Sand), 725 (Dawsons Mill), 728 (Ed Jones), 737 (Mountain Vista), 747 (Preddy Creek),
753 (Paces Store), 760 (Red Hill Schl), 774 (Bear Creek/Appleberry Mtn), 776 (Buck Mtn Ford),
784 (Doctors Xing), 795 (Blenheim), 805 (Henderson), 811 (Jones Mill), 812 (Jim Lane), 824
(Patterson Mill), and 856 (Burton Ln).
(Albevanna Springs), 627 (Porters), 633 (Heards Mtn), 634 (Spring Valley), 635 (Miller Schl),
638 (Blacks Ln), 651 (Free State), 652 (Old Brook), 656 (Georgetown), 658 (Barracks Farm),
665 (Millington), 669 (Lakeside), 675 (Lake Alb), 676 (Tilman), 677 (Old Ballard), 691 (Jarmans Gap)
693 (Still House Creek), 694 (Miller Lake), 696 (Edge Valley), 701 (Alberene Church), 706
(Dudley Mtn), 708 (Red Hill), 710 (Taylors Gap), 712 (Plank), 713 (Glendower), 717 (Secretarys
Sand), 719 (Alberene), 720 (Harris Creek), 721 (Old Dominion), 727 (Blenheim), 728 (Ed Jones),
729 (Buck Island), 733 (Campbell Farm), 734 (Bishop Hill), 742 (Avon), 761 (Briery Creek), 792
(Stump Town), 793 (Serene Ln), 795 (Blenheim), 846 (Orchard), 854 (Carrsbrook), 866
(Greenbrier), 874 (Woodchuck), 1117 (State Farm), 1135 (Willow Lake), 1137 (Brookhill), 1140
(S Pantops), 1150 (Mill Creek), 1165 (Southern Pkwy), 1401 (Wakefield), 1415 (Idlewood), 1417
(Woodbrook), 1418 (Brookmere), 1421 (Elk Dr), 1427 (Hillsdale), 1428 (Huntington), 1438 (Hilton
Heights), 1695 (Mall Dr).
636 (Batesville), 637 (Dickwoods), 649 (Proffitt), 674 (Clark), 691 (Jarmans Gap), 708 (Dry Bridge)
712 (Coles Rolling), 715 (Esmont), 717 (Secretarys Sand), 782 (Stribling Ext), 787 (Gillums Ridge)
810 (Browns gap/White Hall), 1150 (Mill Creek).

7/3/2007
Rural Rustic Program 2007
Albemarle County
Grading and Pipe Installation (State Forces)
Week of August 1
Week of August 27
Week of September 24
Surface Treatment (Tar and Chip Seal) (Hired Equipment)
Week of July 16
Week of September 17