R/W is currently being negotiated. VDOT, Albemarle County and Luck Stone to are scheduled to meet on March 30th to discuss the construction funding for this project.
R/W phase update: Right-of-Way appraisals and acquisitions continue. Still on schedule for R/W to be clear by November 2007 and utility relocations to begin. This project remains on schedule for a June 2008 advertisement.
Project funding update: Estimated funding shortfall at this time is $5.1 million. Potential cost reductions and additional funding have been identified for $3.9 million leaving total shortfall at $1.2 million
Administrative functions related to the phasing of this project are still ongoing. An exact advertisement date cannot be firmly established until final secondary six year plan funding allocations are in place. At present projected allocations, it is expected the project will be advertised in late 2008 or early 2009.
Aerial Survey completed. Data conversion for use in design is underway and should be completed in late April.
The curve has been staked in the field and a scoping meeting has occurred. Environmental has evaluated impacts and residency staff is developing environmental permits and box culvert information.
Please see attached report regarding rural rustic program.
The project advertisement date will be set for the fall of 2007. The estimate has been revised and funding for the project is in place.
|
Land Development Items |
Total This Month |
Total This Fiscal Year |
|
Special Use Permits and Rezoning Application Review |
5 |
40 |
|
Site Plan Reviews for new Subdivisions |
8 |
88 |
|
New Entrance Plan Reviews |
22 |
127 |
|
Total Permits Processed |
80 |
662 |
|
Utility Permits Processed |
18 |
101 |
|
Inspection of new Subdivision Street conducted |
7 |
84 |
|
Inspection of new entrance conducted |
100 |
909 |
|
Miles of Street Accepted in the State System |
.81 |
4.28 |
|
|
|
|
|
Albemarle - Completed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
ACTION |
|
Albemarle – Being reviewed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
STATUS |
|
810 (Crozet) |
Rt 789 to Rt 240 |
Speed Study requested |
To Traffic 3/22/07 |
|
631 (Rio Rd E) |
Hillsdale & Old Brook |
Request for crosswalks |
To Traffic 3/09/07 |
|
Greene – Being reviewed |
|
|
|
|
RTE |
LOCATION |
REQUEST |
ACTION |
660 (Reas Ford), 665 (Buck Mtn), 663 (Simmons Gap), 672 (Blufton), 684 (Mint Springs), 708
(Dry Bridge), 710 (Taylors Gap), 711 (Burton, 712 (Plank), 717 (Secretarys Sand),
727 (Blenheim), 743 (Earlysville), 810 (Browns Gap), 851 (Dominion), 1427 (Hillsdale) and
1452 (Westfield).
640 (Gilbert Station), 643 (Rio Mills), 671 (Ballards Mill), 672 (Via), 673 (Slamgate), 674 (Clark),
678 (Ridge), 687 (Shiffletts Mill), 702 (Reservoir), 711 (Burton), 712 (Coles Rolling), 713 (Dyers Mill),
722 (Old Green Mtn), 723 (Sharon), 731 (Keswick), 734 (Bishop Hill), 736 (White Mtn/Pughs Store),
745 (Poorhouse), 758 (Smith), 774 (Bear Creek), 778 (Johnsons), 784 (Drs Xing), 811 (Jones Mill),
856 (Justice Farm Ln).
640 (Turkey Sag), 662 (Bleakhouse), 664 (Buffalo River), 668 (Fox Mtn), 672 (Blufton), 684
Mint Springs), 722 (Old Green Mtn).
Tree cleanup on Routes 6, 20, 29, 250, 626 (James River), 627 (Porters), 635 (Miller Schl), 676 (Tilman)
678 (Decca/Ridge), 682 (Broad Axe), 691 (Jarmans Gap), 715 (Esmont), 726 (James River),
727 (Blenheim), 795 (Blenheim), 854 (Carrsbrook) and 1603 (Leeds Ln).
624 (Beazley), 626 (Snow Mtn), 628 (Simmons Gap), 629 (Welsh Run), 630 (Rosebrook), 632
(Wyatt Mtn), 637 (Pocasan Mtn), 638 (Teel Mtn), 642 (Taylor Mtn), 667 (Middle River) and 676 (Shifflett).

Rural Rustic Construction Program 2007
Albemarle County
Grading and Pipe Installation (State Forces)
Week of April 9: Begin construction of Route 769, (Rocky Hollow Road), Duration: 6 weeks
Week of May 14: Begin Construction of Route 647, (Maxfield Road), Duration: 4 weeks
Week of June 4: Begin construction of Route 734, (Bishop Hill Road), Duration: 4 weeks
Week of July 2: Begin Construction of Route 640, (Gilbert Station Road), Duration: 6 weeks
Surface Treatment (Tar and Chip Seal) (Hired Equipment)
Week of May 14: Begin Surface Treatment Paving of:
Route 769 (Rocky Hollow Road), Duration: 2 weeks
Route 744, (Hacktown Road), Duration: 3 weeks
Week of July 9: Begin Surface Treatment Paving of:
Route 647 (Maxfield Road), Duration: 2 weeks
Route 734 (Bishop Hill Road), Duration: 2 weeks
Route 640 (Gilbert Station Road), Duration: 3 weeks
Total Construction Time:
Route 744, Hacktown Road: 3 weeks
Route 769, Rocky Hollow Road: 8 weeks
Route 647, Maxfield Road: 6 weeks
Route 734, Bishop Hill Road: 6 weeks
Route 640, Gilbert Station Road: 9 weeks