8/28/2007
Rural Rustic Program 2007
Albemarle
County
Grading and Pipe Installation (State Forces and Hired Equipment)
Week
of August 27
-
Begin construction of Rte 734,(Bishop Hill Road), Duration: 4 weeks
Week
of August 13
-
Begin Construction of Rte 647, (Maxfield Road), Duration: 4 weeks
Week
of October 1
-
Begin Construction of Rte 640, (Gilbert Station Road), Duration: 6 weeks
Surface Treatment (Tar and Chip Seal) (Hired Equipment)
-
Completed
Surface Treatment Paving:
-
Rte 769 (Rocky
Hollow Road),
-
Rte 744, (Hacktown
Road),
Week
of October 1
-
Begin Surface Treatment Paving;
-
Rte 647 (Maxfield
Road), Duration: 2 weeks
-
Rte 734 (Bishop Hill
Road), Duration: 2 weeks
-
Rte 640 (Gilbert
Station Road), Duration: 3 weeks