Charlottesville Residency Monthly Report


December  2006

 

 

Albemarle County BOS Action Items

David Slutzky

Ken Boyd

Lindsay Dorrier

Dennis Rooker

Dave Wyant

Sally Thomas

 

Construction                                                                                               Active Construction Projects

     BP-7A-05 (District wide bridge painting project)                                                               

·         Barracks Road – Proceeding with incidental cleanup.  Awaiting removal of sea container.

·         Painting of bridges, Routes 690 and 691 over I-64, to be completed on or about 27 Dec 2006; derigging and cleanup to commence thereafter. 

Route 601, Old Ivy Road, 0601-002-6261, SR01 (Emergency Bridge Repair)

·         Deck has been placed.

·         Concrete placed for curb.

·         Forming parapet

·         Completion expected in late January to early February

Bridge Deck Patching and Joint Repair Service Contract

·         Contractor performing nominal deck patching on I-64 Bridges at various locations in western Albemarle County.

                                                                                                                                                                    

Preliminary Engineering

Albemarle County

R/W is currently being negotiated.  After R/W is acquired and utilities are relocated, Luck Stone will construct the project under permit.  Meeting scheduled.

R/W phase update:  An offer has been made for the Replacement Park Land (Total take – Parcel 007) and negotiations are underway.  The appraisals are being prepared for the remaining parcels and offers/negotiations should begin in February 2007.  All R/W should be clear by November 2007 and utility relocations will begin.  Residency Staff is working with County staff to update funding.  This project remains on schedule for a June 2008 advertisement.

Project funding update:  Estimated funding shortfall at this time is $5.1 million.  Potential cost reductions and additional funding have been identified for $3.9 million leaving total shortfall at $1.2 million

Survey update being scheduled to reflect new development and to finalize project estimate.  It appears feasible to split this project into two, with the separation occurring at Jarmans Lake Road.  Updated advertisement and funding schedule to be produced in Six Year Plan update.

The project will only include pedestrian and safety improvements and will not be federal.  Aerial survey is being scheduled.

The curve has been staked in the field and a scoping meeting has occurred.  Environmental is currently assessing impacts.

Culvert and grading operations will begin in the fall of 2006.  The surface will be placed in the spring of 2007.

 
Greene County

It has been determined that the project is not eligible for federal funding.  Funding has been shifted to this project to be fully funded in F.Y. 2008.  Transportation funding shortfall will possibly extend ad date.

 

Planning, Permits and Land Development

 

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

6

24

Site Plan Reviews for new Subdivisions

5

59

New Entrance Plan Reviews

34

69

Total Permits Processed

81

331

Utility Permits Processed

7

46

Inspection of new Subdivision Street conducted

15

39

Inspection of new entrance conducted

109

489

Miles of Street Accepted in the State System

.20

1.29

 

Traffic Engineering

 

Albemarle - Completed

 

 

RTE

LOCATION

REQUEST

ACTION

600 (Watts Passage)

Int Rt 1005 (McClary Ct)

School Bus Stop Ahead

Completed 12/14/06; sent to sign crew to post

649 (Profitt)

Between 29 & 505

School Bus Stop Ahead

Completed 11/28/06; sent to sign crew to post

 

 

 

 

 

 

 

 

 

Albemarle – Being reviewed

 

 

RTE

LOCATION

REQUEST

STATUS

616 (Black Cat)

Between 250 & FCL

Safety & speed study

To Traffic 12/13/06

665 (Millington)

From 671 (Ballards Mill)

Speed reduction

To Traffic 12/13/06

250

From Ivy to West Leigh

Request center turn arrows

To Traffic 12/20/06

6

Main Street (Scottsville)

Paint center lines

To Traffic 12/20/06

731 (Keswick)

Entire road

Paint center lines

To Traffic 12/20/06

 

 

 

 

 

 

 

 

 

 

 

 

 

Greene – Being reviewed

 

 

RTE

LOCATION

REQUEST

ACTION

 

 

 

 

 


 

 

Maintenance work completed

Albemarle County

626 (James River), 631 (Rio), 641 (Burnley Station), 652 (Old Brook), 654 (Barracks), 664 (Markwood),

665 (Buck Mtn/Millington), 684 (Mint Springs), 690 (Greenwood Station), 810 (Crozet/White

Hall/Boonesville), and 847 (Watts Station).

633 (Heards Mtn), 638 (Blacks Lane), 640 (Gilbert Station), 641 (Burnley Station), 643 (Rio Mills),

659 (Woodburn), 668 (Fox Mtn), 670 (Damon), 672 (Blufton), 673 (Breakheart/Slam gate), 678 (Ridge),

682 (Broad Axe), 683 (Shelton Mill), 684 (Half Mile Branch), 691 (Jarmans Gap), 702 (Reservoir),

704, (Fortune), 708 (Secretarys/Red Hill), 712 (Coles Rolling), 713 (Glendower), 714 (Riding Club),

716 (Forsyth), 720 (Harris Creek) 722 (Old Green Mtn), 725 (Dawsons Mill), 728 (Ed Jones), 734

(Bishop Hill), 736 (White Mtn), 737 (Mtn Vista), 745 (Poorhouse), 746 (Fosters Branch), 760

(Red Hill School), 761 (Briery Creek), 762 (Rose Hill Church), 769 (Rocky Hollow), 774 (Bear Creek),

792 (Stump Town), 793 (Serene) and 824 (Patterson Mill).

(Burnley Station), 649 (Proffitt), 664 (Markwood), 665 (Buck Mtn), 668 (Fox Mtn), 691 (Jarmans Gap)

745 (Arrowhead Valley, 784 (Doctors Crossing), 854 (Carrsbrook), and 1496 (Oak Forest).

698(Hungrytown), 738 (Morgantown), 810 (White Hall/Browns Gap), and 1165 (Southern Parkway).

726 (James River), 729 (N Milton), 746 (Fosters Branch), and 753 (Paces Store).

weather until spring on this project.  Pipe work to continue as weather permits.)

 

Greene County

628 (Simmons Gap), 629 (Welsh Run), 630 (Rosebrook), 637 (Pocosan Mtn)), 638 (Turkey Ridge/Teel Mtn), 642 (Simms/Taylor Mtn), 646 (Blue Run), 668 (Peyton Lane), and 676 (Shifflett).

 

Planned Maintenance work – January 2006

weather until spring on this project.  Pipe work to continue as weather permits.)


 

 

Maintenance Budget

 

 