Allan D. Sumpter                                                                                                                                     Virginia Department of Transportation

Charlottesville Residency Administrator                                                                                                                                     701 VDOT Way

                                                                                                                                                                                  Charlottesville, VA  22911

 

Charlottesville Residency Monthly Report


November  2006

 

 

Albemarle County BOS Action Items

David Slutzky

Ken Boyd

Lindsay Dorrier

Dennis Rooker

Dave Wyant

Sally Thomas

 

Construction                                                                                               Active Construction Projects

BP-7A-05 (District wide bridge painting project)                                                                       

PM-7B-06 (Primary roads paving schedule)

·         Schedule is complete.

Route 601, Old Ivy Road, 0601-002-6261, SR01 (Emergency Bridge Repair)

·         Beam has been placed.  Forming underway.  Anticipating deck being poured week of December 11th.  Completion expected in late January.

Preliminary Engineering

Albemarle County

R/W is currently being negotiated.  After R/W is acquired and utilities are relocated, Luck Stone will construct the project under permit.

Transportation funding shortfall will possibly extend ad date.  Right of Way plans have been approved.  The Notice to Proceed for right of way acquisition was issued October 4, 2006.  Funding is being addressed to keep on schedule.

Advertisement date will be adjusted to show an August 2009 ad.  R/W plans are expected to be signed by July 30, 2007.

Preliminary schedule was submitted to Dennis Rooker on August 23rd.  The project will only include pedestrian and safety improvements and will not be federal.

This project is on hold as funds may need to be transferred to Rt 643 at the request of the county.  District has submitted the bridge replacement projects to Richmond for Federal funds consideration.

The curve has been staked in the field and a scoping meeting has occurred.  Environmental is currently assessing impacts. 

Culvert and grading operations will begin in the fall of 2006.  The surface will be placed in the spring of 2007.

 
Greene County

It has been determined that the project is not eligible for federal funding.  Funding has been shifted to this project to be fully funded in F.Y. 2008.  Transportation funding shortfall will possibly extend ad date.

 

Planning, Permits and Land Development

 

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

6

24

Site Plan Reviews for new Subdivisions

5

59

New Entrance Plan Reviews

34

69

Total Permits Processed

81

331

Utility Permits Processed

7

46

Inspection of new Subdivision Street conducted

15

39

Inspection of new entrance conducted

109

489

Miles of Street Accepted in the State System

.20

1.29

 

Traffic Engineering

 

Albemarle - Completed

 

 

RTE

LOCATION

REQUEST

ACTION

22 (Louisa Rd)

Near Cismont Farm

School Bus Stop Ahead

To District sign crew on 11/6/06

600 (Watts passage)

Fr Rt 20 to Rt 29

Safety Review/speed study

Installed signs on 11/6/06

1425 (Angus Rd)

 

Speed study

To sign crew 11/14/06

 

 

 

 

 

 

 

 

Albemarle – Being reviewed

 

 

RTE

LOCATION

REQUEST

STATUS

250

RT 1116 (Riverbend Dr)

Request mixed usage lane

To Traffic 10/26/06

684 (Half Mile Branch)

 

Safety review of Route

To Traffic 10/31/06

691 (Hilltop St)

 

Speed study for centerlines

To Traffic 11/03/06

720 (Harris Creek Rd)

 

Speed study/child playing signs

To Traffic 11/9/06

 

 

 

 

 

 

 

 

 

 

Greene – Being reviewed

 

 

RTE

LOCATION

REQUEST

ACTION

33

Int of Route 622

Signal study

Field review 10/19/06; analysis pending.

 


 

 

Maintenance work completed

Albemarle County

708 (Secretary), 710 (Taylors Gap), 742 (Avon St Extd), 795 (Presidents), 810 (White Hall/Boonesville),

1575 (Austin).

633 (Heards Mtn), 636 (Batesville), 639 (Harrington), 640 (Gilbert Station), 641 (Burnley Station),

643 (Rio Mills), 645 (Magnolia), 646 (Lovers Ln), 659 (Woodburn), 667 (Catterton), 668 (Fox Mtn),

672 (Blufton), 673 (Breakheart/Slam gate), 678 (Ridge), 688 (Midway), 689 (Pounding Creek),

697 (Sutherland), 699 (Boaz), 704, (Fortune), 711 (Burton), 712 (Coles Rolling), 714 (Riding Club),

715 (Esmont), 716 (Forsyth), 717 (Secretarys Sand), 718 (Murrays), 722 (Old Green Mtn),

723 (Sharon), 724 (Lewiston Ford), 726 (James River), 728 (Ed Jones), 734 (Bishop Hill), 735 (Mt Alto),

736 (Pughs Store), 737 (Mtn Vista), 746 (Fosters Branch), 761 (Briery Creek), 769 (Rocky Hollow),

774 (Bear Creek), 795 (Blenheim), 807 (Hawkshill), 816 (Willow Dale), and 829 (Horseshoe Bend).

664  (Markwood), and 800 (Schuyler).

668 (Fox Mtn), 673 (Breakheart/Slam gate), 704 (Fortune), 713 (Glendower), 784 (Doctors Crossing),

792 (Stump Town), 810 (White Hall), 854 (Carrsbrook), and 1446 (George Rogers).

632 (Faber), 639 (Harrington), 641 (Burnley Station), 646 (Lovers Ln), 653 (Old Free Union),

665 (Buck Mtn), 675 (Lake Alb), 676 (Tilman), 677 (Old Ballard), 678 (Decca), 699 (Boaz),

708 (Red Hill), 718 (Murray), 722 (Old Green Mtn), 723 (Chestnut Grove), 724 (Lewiston Ford),

805 (Henderson), 807 (Hawkshill), 810 (White Hall/Browns Gap), 824 (Patterson Mill),

839 (Whippoorwill), and 840 (Covesville).

(Gilbert Station) 641 (Burnley Station), 671 (Millington), 675 (Lake Alb), 677 (Bloomfield),

682 (Broad Axe), 729 (N Milton), 731 (Keswick), 736 (Pughs Store), 745 (Arrowhead Valley),

748 (Broken Sun), 771 (Glenaire), 784 (Doctors Crossing), 810 (Browns Gap Trnpk), 1177 (Dunlora), and

1427 (Northfield).

spring on this project.  Pipe work to continue as weather permits.)

725 (Dawsons Mill), and 810 (Browns Gap).

 

Greene County

 

Planned Maintenance work – December 2006

spring on this project.  Pipe work to continue as weather permits.)

 

Maintenance Budget

 

 

Return to regular agenda