James S. Utterback, PMP                                                                                                                        Virginia Department of Transportation

Charlottesville Residency Administrator                                                                                                                                     701 VDOT Way

                                                                                                                                                                                  Charlottesville, VA  22911

 

Charlottesville Residency Monthly Report


April  2006

 

 

 

Construction                                                                                               Active Construction Projects

 

0053-002-101, C501, B601 Route 53 (Buck Island Creek bridge replacement project)        

    Original completion date:     11/1/2005                   Award amount:  $1,644,187

   Estimated completion date:  05/01/06                    Est. completion amount: $1,534,662.63

        Project is complete pending final acceptance by the Department.

 

BP-7A-05 (District wide bridge painting project)                                                                      

    Original completion date:     10/31/2005                 Award amount:  $1,556,670

    Estimated completion date:  9/1/2006                    Est. completion amount: $1,556,670

 

PM-7I-05 (Secondary roads paving schedule in Charlottesville and Louisa Residencies)

      Original completion date:    6/1/06                       Award amount:  $2,944,001.95

      Estimated completion date:  6/1/06                      Est. completion amount:  $3,224,049.45

 

PM-7B-06 (Primary roads paving schedule)

      Original completion date:  12-1-06                       Award amount:  $1,868,560.78

      Estimated completion date:  12-1-06                    Est. completion amount: $1,868,560.78

 

SS-7B-06 (Slurry Seal)

      Original completion date:  9/1/06             Award amount:  $322,191.98

      Completion date:  4/25/06                                   Est. completion amount:  $307,191.98

 

(NFO) BR06-002-105,M500  (I-64 Eastbound Bridge over The Rivanna River & CSX  deck repair)

      Original Completion date: 6/23/06                       Award amount:  $747,924.96

      Estimated completion date: 6/23/06                     Est. completion amount:  $747,924.96

 

 

Preliminary Engineering

Albemarle County

 

On schedule for spring 2008 Construction with design in progress.  Plan to meet with county staff in April to discuss construction advertisement and funding.

On schedule for a June 2008 Ad Date.  Right-of-way is currently updating estimates, performing title searches, and updating plans to reflect information provided by those title searches.

 

The Public Hearing was held on March 30, 2006, and comments are being collected.

This project has been split into three portions (2 bridges w/approaches and a gravel road section).  This project will improve the gravel road section. Right of way and preliminary engineering is underway for a Dec 2007 ad date.

The standards are being considered due to proposed quarry opening along the road improvement area.  Currently contacting land owners for donation of right of way along the improvement area.  Plan to meet with county staff in May and review proposed improvements.

 
Greene County

 

Project is on schedule for December 2006 Ad Date. 

 

Planning, Permits and Land Development

 

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

8

44

Site Plan Reviews for new Subdivisions

5

101

New Entrance Plan Reviews

13

95

Total Permits Processed

77

638

Utility Permits Processed

21

192

Inspection of new Subdivision Street conducted

8

92

Inspection of new entrance conducted

98

918

Miles of Street Accepted in the State System

1.17

5.69

 

Traffic Engineering

 ALBEMARLE

 

Albemarle - Complete

 

 

RTE

LOCATION

            ITEMS REQUESTED

       ACTION TAKEN

29

 

Rio intersection

 

Request Yield to Oncoming Traffic Sign

Recommend no U turn sign on Rt 29

654

At Colonnades

Request pedestrian crossing

To sign crew 1/18/06

1411

Inglewood

Speed Study and traffic count

Speed compliant

1430

Solomon

Speed study and traffic count

Speed compliant

654

Barracks Road Ramps

Request crosswalk at ramps

Not recommended

 

 

 

Albemarle Under review

 

 

RTE

LOCATION

            ITEMS REQUESTED

       ACTION TAKEN

29

At 1670

Request for intersection signage

Under review

29

Boulder Road

Request to add strobe light to signals

Under review

631

Old Lynchburg Rd

V/C Ratio request

Under review

631

Putt Putt

Request for traffic signal

Under review

640

Rt 784 to 641

Reduce speed & post this section

Under review

641

Rt 29 to Advance Mills

Request full signalization

Under review

665

Buck Mountain Rd

Request lower speed limit near church

Under review

688

Various locations

Traffic counts

Under review

743

At 676

Flashing light/extent turn lane

Under review

781

Sunset Avenue

Request traffic count

Under review

810

Between 614 and 674

Request for speed study

Under review

 

 

 

Greene - Complete

 

 

RTE

LOCATION

            ITEMS REQUESTED

       ACTION TAKEN

 

 

 

 

Greene - Under review

 

 

230

 

Stanardsville to Madison CL

Request for truck restriction

Under review

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Maintenance work completed

 

Albemarle County

748, 611, 640, and 600.

859, 1473, 673, 631, 795, 620, and 724.

 
Greene County

 

  

Planned Maintenance work May  06

 

 

 

Maintenance Budget

 

Return to regular agenda