James S. Utterback, PMP                                                                                                                        Virginia Department of Transportation

Charlottesville Residency Administrator                                                                                                                                     701 VDOT Way

                                                                                                                                                                                  Charlottesville, VA  22911

 

Charlottesville Residency Monthly Report

September  2005
 

 

 

Construction                                                                                           Active Construction Projects

Route 649 (Airport Road improvement project) 0649-002-158, C501                          

   Original completion date:     9/2/2005                     Award amount:  $4,820,177

   Estimated completion date:  11/1/2005                    Est. completion amount: $4,744,289.84

       Roundabout is complete with exception of the airport connection.  Paving for proposed Rte. 649 eastbound lanes. nearly complete.

Route 53 (Buck Island Creek bridge replacement project) 0053-002-101, C501, B601        

    Original completion date:     11/1/2005                   Award amount:  $1,644,187

   Estimated completion date:  11/1/2005                   Est. completion amount: $1,645,387.35

        North and south side abutments are complete with steel beams placed.

BP-7A-05 (District wide bridge painting project)                                                                      

    Original completion date:     10/31/2005                 Award amount:  $1,556,670

    Estimated completion date:  10/31/2005                 Est. completion amount: $1,556,670

         Old coatings removed and primer coating applied to Rte. 691 bridge over I-64 and the I-64 bridges over the C&O ROW.

PM-7B-05 (Asphalt pavement overlay)

     Original completion date:   12/1/2005                    Award amount:  $3,699,919.31

            Estimated completion date:  12/1/2005                 Est. completion amount:  $3,806,623.59

PM-7I-05

      Original completion date:    6/1/06                       Award amount:  $2,944,001.95

      Estimated completion date:  6/1/06                      Est. completion amount:  $3,288,649.45

Note:  Asphalt surface overly on Rte. 29 north and south bound lanes fronting the Hollymead Town Square. Development was added to this contract by work order.  This work was completed.

BR-7C-05 (Bridge deck repairs and epoxy overlay)

      Original Completion Date:  11/1/05                     Award amount:  $296,055.50

      Estimated Completion Date:  11/1/05                  Est. completion amount:  $326,867.68

TP-7B-05 (Secondary road pavement markings)

      Original Completion Date:  8/24/05                     Award amount: $112,455.31

      Estimated Completion Date:  10/29/05                 Est. completion amount:  $112,455.31

Note:  Original Contract Date is in error.  Contract General Notes indicate the correct completion date of 10/29/05.

   

 

Preliminary Engineering

 
Albemarle County

On schedule for spring 2008 Construction with ROW acquisition to begin in October 2005.

On schedule for a June 2008 Ad Date with ROW acquisition scheduled to begin in December 2005.

The Public Hearing is rescheduled for spring 2006.

This project scoping meeting was held on September 29, 2005.  The project will require the replacement of two bridges and a significant amount of rock removal to complete.  The estimate for the entire project is to be revised and the project split into segments for construction.  The ROW on the east side is under negotiation with the UVA Foundation and hinges on some previous proffers regarding buffers they need to maintain for their development.

This project has been moved forward on the plan.  The Scoping for the project was held on September 29, 2005.  The ROW is available and the project will be scheduled for construction in the spring, 2007, pending utility relocations.

Phase 2 from Doctors Crossing, Route 784, to Ashley Road, Route 1094, is scheduled to start first week in October and should be completed by the end of October.

 
Greene County

Project is on schedule for December 2006 Ad Date. 

 

 

 

Planning, Permits and Land Development

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

4

9

Site Plan Reviews for new Subdivisions

13

15

New Entrance Plan Reviews

6

16

Total Permits Processed

59

128

Utility Permits Processed

20

39

Inspection of new Subdivision Street conducted

11

17

Inspection of new entrance conducted

85

177

Miles of Street Accepted in the State System

0.53

0.53

 

 

Traffic Engineering

 

 

 Maintenance work completed

Albemarle County
 
Greene County

 

Planned Maintenance work October  05

 

Maintenance Budget

Return to regular agenda