James S. Utterback, PMP                                                                                                                        Virginia Department of Transportation

Charlottesville Residency Administrator                                                                                                                                     701 VDOT Way

                                                                                                                                                                                  Charlottesville, VA  22911

 

Charlottesville Residency Monthly Report

August  2005

 

 

Construction                                                                                               Active Construction Projects

Route 649 (Airport Road improvement project) 0649-002-158, C501                          

   Original completion date:     9/2/2005                     Award amount:  $4,820,177

   Estimated completion date:  11/1/2005                    Est. completion amount: $4,820,177

       Traffic is running on the completed new westbound lanes of Rt 649.  New eastbound lanes complete through base asphalt.

Route 53 (Buck Island Creek bridge replacement project) 0053-002-101, C501, B601        

    Original completion date:     11/1/2005                   Award amount:  $1,644,187

   Estimated completion date:  11/1/2005                   Est. completion amount: $1,644,187

         The north and south bridge abutments and wing walls completed to bridge beam seat elevation.

BP-7A-05 (District wide bridge painting project)                                                                      

    Original completion date:     10/31/2005                 Award amount:  $1,556,670

    Estimated completion date:  10/31/2005                 Est. completion amount: $1,556,670

         Eastbound and westbound I-64 bridges over Rte. 781 completed.  The Rte. 690 bridge over I-64 nearly complete.

PM-7B-05 (Asphalt pavement overlay)

     Original completion date:   12/1/2005                    Award amount:  $3,699,919.31

            Estimated completion date:  12/1/2005                 Est. completion amount:  $3,699,919.31

PM-7I-05

      Original completion date:    6/1/06                       Award amount:  $2,944,001.95

      Estimated completion date:  6/1/05                      Est. completion amount:  $3,213,649.45

Note:  Asphalt surface overly on Rte. 29 north and south bound lanes fronting the Hollymead Town Square Development will be added to this contract by work order.

BR-7C-05 (Bridge deck repairs and epoxy overlay)

      Original Completion Date:  11/1/05                     Award amount:  $296,055.50

      Estimated Completion Date:  11/1/05                  Est. Completion Amount:  $296,055.50

TP-7B-05 (Secondary road pavement markings)

      Original Completion Date:  8/24/05                     Award amount: $112,455.31

      Estimated Completion Date:  8/24/05                  Est. Completion Amount:  $112,455.31

Maintenance work completed

Albemarle County

third cycle primary.

638, 704, 714, 631, 722, 646, 639, 642, 637, 601, 629, 806, 634, 605, 636, 745, 702, 824, 691.

 
Greene County

   

 

 

Preliminary Engineering

 
Albemarle County

 

On schedule for spring 2008 Construction with ROW acquisition to begin in August 2005.

On schedule for a June 2008 Ad Date with ROW acquisition scheduled to begin in December 2005.

Has been rescheduled for December 2009 Ad Date.  The Public Hearing is rescheduled for Spring 2006.

On schedule for a December 2007 Ad Date.  The ROW for this gravel road project is only partially available.

Construction on Phase 1 was completed on August 22, 2005, using State Forces.  Phase 2 from Doctors Crossing, Route 784, to Ashley Road, Route 1094, is scheduled to begin construction during the 2nd week of September.

 

Greene County

 

Project is on schedule for December 2006 Ad Date. 

 

Planning, Permits and Land Development

 

Land Development Items

Total This Month

Total This Fiscal Year

Special Use Permits and Rezoning Application Review

4

4

Site Plan Reviews for new Subdivisions

8

8

New Entrance Plan Reviews

9

19

Total Permits Processed

48

48

Utility Permits Processed

19

19

Inspection of new Subdivision Street conducted

11

11

Inspection of new entrance conducted

82

82

Miles of Street Accepted in the State System

0.0

0.0

 

  

Traffic Engineering

 

 

 

 

Maintenance Budget

 

 

Planned Maintenance work September  05

 

 

Return to consent agenda
Return to regular agenda