Addendum to Albemarle Hazard Mitigation Plan

May 6, 2005


The following amendments to the plan were made following the April 26 Planning Commission and May 4 Board of Supervisors meeting:

 

 

 

 

 

 

 

Mitigation Action

Community Name:

Albemarle

Category:

Policy, Planning, and Funding

Action Item (Describe):

Create an Emergency Action Plan for the Upper Ragged Mountain Dam

Hazard (s):

Dam Failure

Lead Agency/Department Responsible:

Emergency Management Coordinator

Estimated Cost:

$20,000

Funding Method: (General Revenue, Contingency/Bonds, External Sources, etc.)

Hazard Mitigation Grant Program, Pre-Disaster Mitigation Grant, Flood Control Works/Emergency Rehabilitation Grant, National Dam Safety Program, River Basin Program (Dept. of Agriculture, National Resources Conservation Services), Watershed Protection and Flood Prevention (Dept. of Agriculture, National Resources Conservation Services)

Implementation Schedule:

1-3 years

Priority

Moderate

 