VDOT's  County's Route Number and Name Location Estimated Estimated Description/Comments  
Secondary Proposed    From  - To Advertisement Cost    
Plan Ranking     Date      
===================================================================================================================================================================================
        Month-Year      
0 0 County wide County wide Jun-10 $750,000 signs,pipe,plant mix projects, same funding   
0 0 County wide Traffic mgmt. Program Jun-10 $300,000 Staff working with VDOT and Whippoorwill, Hollymead, Forest Lakes for traffic calming improvements
1 1 625 Hatton Ferry Hatton Ferry Jun-10 $120,000 operation of ferry   
2   West Leigh Drive Rt 250  to .4 mi nor. Rt. 250 Dec-02 $500,000 rural addition, project complete, VDOT requires it to remain on list until all funding is complete. 
3   Corville Farm Road Rt. 691-Greenwood Rd-D.E. Mar-03 $150,000 rural addition, project complete, VDOT requires it to remain on list until all funding is complete. 
4 2 Meadow Creek Parkway Melbourne Rd to Rio Road Jun-08 $17,161,852 two lane desgin approved by County and Comm. Transport. Bd., includes bridge over CSX RR
4 2 Meadow Creek Parkway Bridge over Meadow Creek Jun-08 $2,204,500 (associated with project above)  
5 3 649 Airport Road Route 29 to Route 606 Dec-03 $12,271,456 widen to four lanes, bike lanes,sidewalks,RS98/99 [13411]  
6 4 651 Free State Road Free State  Road Dec-06 $3,350,000 proposal to construct road from Rio Rd to Free St Rd to replace substandard bridge [420]
7 5 Northern Free State Road Route 631 to Route 29   $4,200,000 north/south conn. rd concept/alternatives. to be studied in conj w/ the proposed eastern conn. rd as recom.in the proposed CHART.
8 6 691 Jarmans Gap Road Route 240 to Route 684 Dec-08 $10,500,000 serve increased traf w/ min widening, ped/bike access,RS 1999/00 [2,400]
9 7 649 Proffit Road Rt 29 to 1.6 miles east Jun-12 $9,500,000 improve alignment, urban x-section with bike/sidewalk,RS 2004/2005 [2273]
11 8 656 Georgetown Road Route 654 to Route 743   $3,200,000 spot improvement, pedestrain access,urban cross-section, RS 97/98 [17,000]
10 9 Southern Parkway Avon Str. to Fifth Str.     Extend to 5th St., with pedestrian/bike facility, and Neighborhood street design/speed
12 10 601 Old Ivy Road Ivy Road to 250/29 Byp   $7,200,000 widen, improve alignment bike/sidewalk access,RS 2000/01 [4,800]
  11 679 Grassmere Road .25 miles south of Rt 738 Jun-04 $100,000 Railroad crossing with no lights or gate [485]  
  12 781 Sunset Avenue NCL to Fifth St Extended     spot and inter. Improve., urban x-sect, upgrade 2 lane.RS 2005/06, ped/bike access[1,100]
  13 631 Old Lynchburg Road 1.35 MI. S. I-64 to Rt.708      spot improvements at various locations,RS 2001/02   [2,100]  
  14 726  James River Road Route 795 to Route 1302     spot improvement to improve sight distance,RS 2002/03 [2000]  
  15 Hillsdale Drive Greenbrier Dr. to Seminole Sq.   new connector road between Hillsdale Rd and Hydraulic Rd, to be constructed with urban funds
  16 795 Blenheim Road Intersection of Route 790     intersection improvement. [670]  
  17 Eastern Avenue Route 240 to Route 250     interconnect future neighborhoods str, proj. to include RR underpass and bridge over Lickinghole Crk 
  18 631 Rio Road Rio Rd @ Pen Park Lane     Inter. improve. requested by City, to be funded from private source [23,000]
  19 708 Dry Bridge Road Railroad overpass     school transp. Dept. request, low weight limit  
  20 643 Polo Grounds Road Route 29 to Route 649     public req. to improv align, spot improv. safety related, RS 2004/05 [1000]
  21 743 Hydraulic Road Intersection with Rt. 29 (29H250)   improvements recommended from 29H250 Phase 2 Study [20,000]
  22 866 Greenbrier Drive Intersection with Rt. 29 (29H250)   improvements recommended from 29H250 Phase 2 Study [8,800]
  23 676 Tilman Road Road Intersection of Route 250     intersection improvement,RS 2003/04  [4,800]  
  24 614 Garth Road  Intersection of Rt. 676     intersection improvement, public request  [3400]  
  25 601 Garth Road Intersection of Route 658     add turning lane at Barracks Farm Road, CATS recomm.                       [6,300]
  26 738 Morgantown Road at Route 250     close west ramp and construct tapered turn lane  [1200] [1200]
  27 676 Woodlands Road Intersection of Route 601     intersection improvement  [5400]
  28 616 Union Mill Road FCL to Route 759     improve alignment [5,000]
  29 606 Dickerson Road Route 649 to Route 743     improve to handle projected traffic, CHART recommendation, RS 2002/03 [6,700]
  30 654 Barracks Road  Intersection of Route 1001     intersection improvement  [6400]
  31 1403 Berkmar Extension  Hilton Heights Rd to Town Center Rd   new road to serve as parallel road to Rt. 29  
  32 Main Street  Crozet Avenue to Eastern Avenue   new road as recommended in the Crozet Master Plan  
  33  Town Center Rd Extended  end of Town Center Rd to Airport Road    new road to serve Hollymead development area  
  34 1520 Hollymead Dr Ext Route 29 to Rt. 743     new road to serve hollymead  development area  
  35 Meadows Road Rt. 691 to Rt. 250     new road as recommended in the Crozet Master Plan  
  36 678 Owensville Road Intersection of Route 250     intersection improvement [3,400]  
  37 732 Milton Road Intersection of 762     spot improvement, requested by public [1,100]
  38 810 White Hall Road Intersection of Route 789     Intersection improvement. RS 2003/04.[1,800]   
  39 795 James Monroe Pky Intersection of Route 53     recommended from CATS,  intersection improvement.RS 2005/06 [3,000]
    641  Frays Mill Road Rt. 641 @ Jacob Run     install box culvert,RS 2005/06, not a County priority,a VDOT recommendedsafety project
    641  Frays Mill Road Rt. 641 @ Jacob Run     install box culvert, no County Priority,a VDOT recommended safety project
  40 Fifth St Connector Rd Fifth Street to Avon Street     connector road NORTH of I-64, urban cross section  
  41 Rt. 29 parallel road Polo Grounds Rd to Hollymead Dr.    new road  
  42 743 Earlysville Road Rivanna River to Rt 643     public request to improv align, spot improv. safety related.RS 2004/05 [8,400]
  43 729 Milton Road Rt. 53 to Rt. 1120     improve road geometrics, two lane rural section                                     [4400]
  44 663 Simmons Gap Rd at int. of Rt. 604 - Buffalo River Rd   site distance improvement [1000]
  45 684 Half Mile Branch Road Rt. 691 to Rt. 797     spot/safety improvement to serve increased traffic w/  minimum widening [680]
  46 702 Reservoir Road Fontaine Ave. Ext to Dead end   paving and spot improvements at most dangerous locations [1900]
               
Projects in bold are in the  Development Area. Projects in bold and in italics are new on this year's priority list    
  47 641 Burnley Station Road Norfolk Southern RR     bridge project with low sufficiency rating  [340]
  48 602 Howardsville Tnpk .01 miles south Route 626     Railroad crossing with no lights or gate                                              [410]
  49 640 Gilbert Station Road Norfolk Southern RR     bridge project with low sufficiency rating  [170]
  50 642 Red Hill Depot Road .28 miles northeast Rt.708     Railroad crossing with no gate  [80]
  51 671 Millington Road Intersection of Route 665     intersection improvement [370]
  52 692 Plank Road Route 29 to Route 712     spot improvements, safety related                                                        [1,400]
  53 708 Red Hill Road Route 20 to Route 29     improve alignment                                                                              [1,700]
  54 676 Woodlands Road Route 614 to Route 1050     spot improvements at several points, CATS recommendation                [2,600]
  55 691 Park Road Park Road to Route 250     extend to eastern 240/250 street system [640]
  56 678 Decca Lane Intersection of Route 676     improve  intersection, located near school, CATS recommendation          [140]
  57 743 Advance Mills Road At Jacobs Run     improve approach to bridge [1,000]
  58 795 Hardware Street Near inter. with Rt. 20     spot improvement, requested by Scottsville [710]
  59  732 Milton Road at Rt. 53     intersection improvement, public request [1100]
  60 622 Albevanna Springs Rd Intersection of Route 795     intersection improvement [1000]
  61 622 Albevanna Springs Rd Intersection of Route 773     intersection improvement [1000]
  62 680 Browns Gap Tnpk Rt. 240 to Rt. 810      spot improvements, public request                                                       [700]
  63 611 Jarmans Gap Road Off  Route 691     Railroad crossing with no gate  [210]
  64 1310 Ferry Street .05 miles south of Rt. 6     Railroad crossing with no gate [80]
  65 601 Free Union  at Tasmania Drive     install culvert to prevent requent flooding [1000]
  66 682 Broadaxe Road Off Dick Woods Road     spot improvements, public request [140]
  67 813 Starlight Road Off Route 712     school request,needs turn-around space [60]
  68 654 Barracks/ Garth Road Georgetown Rd. to Rt. 601     pave shoulders  and/or off road trail [22,000]
  69 631 Rio Road  Meadow Creek Pwy to Stonehenge   upgrade to urban x-section, sidewalk and bikelanes [24,000]
  70 742 Avon Street Ext.  City limits to Mill Creek South   improve to urban cross section [1200]
  71 Road Paving Projects* See attached        
   * The County has established two separate lists (Attached) for road paving projects: Regular Paving and Rural Rustic Roads paving.  
               
               
               
               
               

Return to executive summary