DRAFT
ALBEMARLE COUNTY PRIORITY LIST FOR SECONDARY ROAD IMPROVEMENTS FOR UNPAVED
ROADS |
| |
|
|
2004-05 Through 2009-10 |
| |
[SOME PROJECTS MAY NOT BE COMPLETED AS PRIORITIZED DUE TO PROJECT COMPLEXITY
AND/OR AVAILABLE FUNDING] |
| |
|
|
|
|
|
|
Route Number and Name |
Location |
Estimated |
Estimated |
Most |
Description/Comments |
| |
From - To |
Advertisement |
Cost |
Current |
|
| |
|
Date |
Regular/RRR |
Traffic Count |
|
|
================================================================================================================================================================================================================================================== |
| |
|
|
|
|
|
| |
PROJECTS THAT QUALIFY FOR REGULAR ROADS PAVING IN PRIORITY RANKING |
| |
|
|
|
|
|
|
737 Mountain Vista Road |
Route 6 to Route 726 |
Completed |
$650,000 |
project completed |
|
708 Secretarys Road |
Route 795 to Route 620 |
Feb-04 |
$1,170,989 |
construction to begin Spring 2004 |
|
640 Gilbert Station Road |
Route 641 to Route 747 |
Completed |
|
completed in Fall 2003 with private resources in conjunction with adjacent
development |
|
606 Dickerson Road |
Route 850 to Route 1030 |
Feb-08 |
$1,400,000 |
[360] |
Public request. At current ranking due to traffic count. |
|
643 Rio Mills Road |
Rt. 29 to portion paved -(due to length, may be two
projects) |
|
[1900] |
Staff request. At current ranking due to traffic count. |
|
606 Dickerson Rd |
Rt. 1030 to Rt. 763 |
|
|
[530] |
Staff request. At current ranking due to traffic count. |
|
647 Maxfield Road |
Rt. 22 to Dead End |
|
$500,000 |
[470] |
Public request. At current ranking due to traffic count. |
|
784 Doctors Crossing |
Route 600 to Route 640 |
. |
$1,238,105 |
[360] |
Public request. At current ranking due to traffic count. |
|
688 Midway Road |
Rt. 635 to Rt. 824 |
|
$200,000 |
[360] |
Public request. At current ranking due to traffic count. |
|
787 Gillums Ridge Rd. |
Route 682 to Route 708 |
|
$350,000 |
[360] |
Public request. At current ranking due to traffic count. |
|
689 Pounding Creek Rd |
Rt. 250 to Rt. 635 |
|
$350,000 |
[340] |
Public request. At current ranking due to traffic count. |
|
712 North Garden Lane |
Rt. 692 to Rt. 29 |
|
$450,000 |
[200] |
Public request. At current ranking due to traffic count. |
|
736 White Mtn Road |
Rt. 636 to Rt. 635 (the sect. btwn Rt. 635 and 636 does
not meet VDOT require.at this time) |
[200] |
Public request. At current ranking due to traffic count. |
|
640 Gilbert Station Road |
Rt. 747 to Rt. 784 |
|
$600,000 |
[200] |
Public request. At current ranking due to traffic count. |
|
712 Coles Crossing Rd |
Rt. 713 to Rt. 795 |
|
$1,250,000 |
[160] |
Public request. At current ranking due to traffic count. |
|
645 Magnolia Rd |
Rt. 608 to Orange CL |
|
|
[140] |
Public request. At current ranking due to traffic count. |
|
682 Broad Axe Road |
Rt. 637 to to current paved sections |
|
[140] |
Public request. At current ranking due to traffic count. |
|
678 Decca Lane |
Route 676 to Route 614 |
|
|
[140] |
Public request. At current ranking due to traffic count. |
|
712 North Garden Lane |
Rt. 29 to Rt. 760 |
|
|
|
This project will be paved as part Rt. 712 -btwn Rt. 713 to Rt. 795 |
|
605 Durrett Ridge Road |
Rt. 743 to Swift Run (including bridge) |
|
[120] |
Public request. At current ranking due to traffic count. |
|
723 Sharon Road |
Route 6 to Route 626 |
|
|
[100] |
Public request. At current ranking due to traffic count. |
|
674 Sugar Ridge Road |
Route 614 to Route 673 |
|
|
[100] |
Public request. At current ranking due to traffic count. |
|
707 Blair Park Road |
Rt. 691 to Dead end |
|
|
[70] |
Public request. At current ranking due to traffic count. |
|
600 Stony Point Pass |
2.5 mileswest to Rt. 20 |
|
|
[50] |
Public request. At current ranking due to traffic count. |
| |
|
|
|
|
|
|
Projects in bold and in italics are new on this year's priority list. |
|
|
|
|
|
VDOT has not determined cost estimates for all unpaved road projects. |
|
|
|
|
The Right-of-Way for all unpaved road requests is undetermined until two or
three years before estimated advertisement date. |
|