Project Scope

Constructing a vehicle sallyport at the Courthouse to facilitate the Sheriff's safe transport of detainees to and from court.  Included were remote gate controls from the Sheriff's Office and additional landscaping.


Project Manager: R. Lilley Construction Start Date: June 2007
Design Firm: DJG, Inc Completion Date: January 2008
General Contractor: Harrisonburg Construction Project Budget: $463,000