Project Management Division  |  Crozet Library
brown-horizontal-line

Crozet Library
Parking Lot and Library Building

Project Scope

  • Design and construction of a parking lot for 53 vehicles as first phase of library development.
  • Design and construction of a 23,000 square foot, 2-story, library facility.
  • Click here for additional information/progress on the new Crozet Library.
Project Manager:  Ron Lilley
Design Firm:  Grimm + Parker Architects

Total Project Budget for Parking Lot and Building:  $8,685,591 (design, land acquisition, construction)
 
Library Construction:
General Contractor:  MB Contractors, Inc.
Construction Start Date:  July 2012
Substantial Completion Date:  June 2013

  • Construction Change Orders:
    #1 approved 9/12/12 for temporary slope drain and revisions to waterline connection required by ACSA ($5,323).
    #2 approved 9/12/12 for waterline changes in Crozet Ave and change from 3500-lb elevator to 2500-lb elevator ($54,374).
    #3 approved 11/15/12 for locating fiber optic line in Crozet Ave and additional waterproofing at basement ($2,865). 
    #4 approved 12/7/12 for floor box revisions (electrical) and increase in steel column size ($14,362).

    #5 approved 2/12/13 for mechanical breaker change & sprinkler relocation ($2,855).
  • Contract awarded to MB Contractors, Inc., for the total base bid amount of $5,771,000, plus additive bid items 1-3 totaling $39,000, for a total contract amount of $5,810,000. Notice to Proceed issued for work to commence on July 1, 2012.

 Crozet Library Rendering


Parking Lot:
General Contractor: Linco, Inc.
Construction Start State: August 2011
Substantial Completion Date: October 2011

  • Parking Lot complete and opened to public 11/28/11.

 


 
 
 