Project Management Division  |  Carrsbrook Drive Pipe Replacement Project
brown-horizontal-line

On July 1, 2015, the Board of Supervisors approved a construction project to replace a failing underground pipe between the upper and lower lakes along Carrsbrook Drive. The Virginia Department of Transportation and Albemarle County’s Office of Facilities Development will manage construction, which is anticipated to last 4 to 5 weeks. Find the latest project news below.

Project updates will be posted on this webpage and at www.albemarle.org/newsroom. If you have specific questions about the project, please contact Frank Pohl, Senior Project Manager, Albemarle County Office of Facilities Development, by e-mail fpohl@albemarle.org, or by phone at (434) 872-4501 (ext. 7914).


Carrsbrook Drive Pipe Replacement Project Update
11/13/16

Reminder that a full closure of Carrsbrook Drive between Indian Spring Road and Marlboro Court will begin at 7:30 AM Monday morning, November 16, 2015 for the duration of the project. The project is expected to be completed within 4 weeks.

This is a joint-project with the Virginia Department of Transportation (VDOT). Due to the deteriorating condition of the pipes and concerns about a future failure, the project is proceeding as soon as possible.  We regret the inconvenience this will cause, especially over the Thanksgiving Holiday weekend.

East of the closure, motorists should follow the posted detour via Route 652 (Westmoreland Road/Old Brook Road). West of the closure, Carrsbrook Drive will remain accessible from Route 29. Access to all driveway entrances will be maintained. Message boards are in place to alert motorists of the upcoming closure.


Carrsbrook Drive in Albemarle Closed November 16 - December 11
11/09/15

A portion of Route 854 (Carrsbrook Drive) in Albemarle County will be closed to through traffic for drainage pipe rehabilitation work beginning at 7:30 a.m. on Monday, Nov. 16. The road will be closed between Route 1432 (North Indian Spring Road) and Route 1419 (Marlboro Court) for approximately four weeks while crews make repairs to a drainage structure under the roadway. The road is expected to reopen the afternoon of Friday, Dec. 11, weather permitting.

East of the closure, motorists should follow the posted detour via Route 652 (Westmoreland Road/Old Brook Road). West of the closure, Carrsbrook Drive will remain accessible from Route 29. Access to all driveway entrances will be maintained.

Message boards are in place to alert motorists of the upcoming closure.

Updates and other real-time travel information can be found on the 511 Virginia website, the free VDOT 511 mobile app or by calling 511 from any phone in Virginia. Local updates are also posted to Twitter.com/VaDOTCulp.


Carrsbrook Drive Update
10/30/15

The Carrsbrook Drive Pipe Replacement Project is finally underway. A pre-construction meeting was held with the ACSA and VDOT this past week and in an effort to complete this important project before the winter and Christmas holidays, the project will begin next week. Please note the following schedule:

  • Week of November 2 – surveying and waterline preparation work will begin. Partial lane closures will occur during this week but traffic in both directions will be allowed through the work zone. Expect and plan for delays.
  • Week of November 9 – Detour signage will be posted and water line outage will occur (Nov 11). The ACSA has issued a letter to all residents affected by the water outage with further details. Partial lane closures will occur during this week but traffic in both directions will be allowed through the work zone. Expect and plan for delays.
  • Week of November 16 – Carrsbrook Drive to be FULLY CLOSED starting on 11/16 for approximately 4 weeks.

This project is being completed out of necessity to ensure the integrity of the road and dam. The previously completed temporary repairs have begun to fail and immediate action is required to protect the public from a potential safety hazard. Your patience and understanding are appreciated.


Carrsbrook Drive Pipe Replacement Project Update
9/16/2015

The Carrsbrook Drive Pipe Replacement Project is getting ready to begin. All access and right-of-way easements have been secured/recorded and the County/VDOT agreement has been executed. A pre-construction meeting will be held with the VDOT contractor in the next few weeks to confirm the work schedule, at which point a public notice will be issued with road closure details. The road closure will affect all traffic for approximately 3-4 weeks as crews complete open-cutting of the road, pipe replacement, and road repair work. Staff will work closely with the Schools Transportation Department to communicate to parents any temporary impacts to the school bus schedule and detour routes.


Carrsbrook Drive Update
8/6/2015

The Carrsbrook Drive Pipe Replacement Project is currently on hold as access and right-of-way easements are secured and recorded. Once this is complete, a notice will be issued to the public at least seven days prior to commencing the work detailing the revised schedule for completion. It is anticipated that the work will take three to four weeks to complete.  Staff will work closely with the Schools Transportation Department to communicate to parents any temporary impacts to the school bus schedule and detour routes.


Construction and Temporary Closure of Carrsbrook Drive
7/16/2015

The Board of Supervisors has approved a construction project along Carrsbrook Drive to replace a failing underground pipe between the upper and lower lakes along Carrsbrook Drive. The Virginia Department of Transportation and Albemarle County’s Office of Facilities Development will begin construction in the next several weeks. Construction is anticipated to last 4 to 5 weeks.

During the replacement, Carrsbrook Drive will be closed to through-traffic at the dam between North Indian Springs Road and Marlboro Court for approximately 3 weeks as the road is open-cut to allow for the excavation and removal of two existing 42-inch deteriorated pipes and the installation of a new 60-inch pipe, manhole and riprap outlet channel.

In addition to the road closure, a 6-inch waterline serving the area will be taken out of service for approximately 8 hours ahead of construction because the waterline conflicts with the repairs. The Albemarle County Service Authority will send letters to affected properties in advance of the outage. Notification boards will also be posted 7 days prior to the outage.

Construction and closure is expected to be completed while schools are on summer break to mitigate impacts to buses/school traffic. The closure will be coordinated with police, fire departments and school summer programs. VDOT has determined that the detour route to be used will be Northfield Road, which connects to Rio Road. Notification boards will be posted 7 days prior to the closing and detour signage will be posted when construction begins.

 


 
 
 
Contact the Department
Project Management Division
401 McIntire Road
Room 420
Charlottesville, VA 22902
434-872-4501
FAX: 434-293-0294