Stone-Robinson Elementary School Parking Reconfiguration

Project Scope

Add 17 permanent bus parking spaces to existing parking lot and expand existing car parking to 101 spaces (from 81).

Project Manager:  H. McInturff Construction Start Date:  June 2011
Design Firm:  Heyward Boyd Architects Substantial Completion Date:  August 2011
Contractor:  Northstar Excavating, Inc. Project Budget:  $165,904

 

 

 

Project Substantially Complete August 2011; minor punchlist items addressed as of October 2011.