Project Management Division  |  Woodbrook Lagoon Enhancement
brown-horizontal-line

Woodbrook Lagoon Enhancement Project

Project Scope

Provide stormwater management for a 250 acre urban watershed through channel improvements, wetlands, and biofiltration. 

Project Manager:  G. Patsch Construction Start Date:  April 2011
Design Firm:  Biohabitats, Inc. Substantial Completion Date:  November 2011 
Contractor:  J. E. Liesfeld Contractor, Inc. Project Budget:  $593,360

 

 

 
 

Status as of October 2011:

  • All earthwork and in-stream structures complete.
  • Storm damage due to heavy rains in late August - temporary repairs in place to prevent further flow damage.
  • Planting to occur this fall.

 