Burley Middle School Track
Project Scope
Installation of a 250M asphalt track and soccer field and related grading and drainage site work on an existing open field.
| Project Manager: R. Lilley |
Construction Start Date: June 2011 |
| Design Firm: Timmons Group |
Substantial Completion Date: August 2011 |
| General Contractor: Haley, Chisholm & Morris |
Project Budget: $202,127 |
- Project Substantially Complete August 2011
- Punchlist Items Complete September 2011

|