Project Management Division  |  AHS Track & Tennis Court
brown-horizontal-line

Albemarle High School Track and Tennis Court

Project Scope

Add two lanes to track, re-surface the track and tennis courts, and minor re-grading of site to address drainage problems. 
 

Project Manager:  M. Breeden  Construction Start Date:  June 2011
Design Firm:  Timmons Group  Substantial Completion Date:  August 2011
General Contractor:  Finley Asphalt & Sealing  Project Budget:  $736,405


Project substantially complete August 2011. 

 

AHS Track


 
 
 
Contact the Department
Project Management Division
401 McIntire Road
Room 420
Charlottesville, VA 22902
434-872-4501
FAX: 434-293-0294
Email the Department