Project Management Division
brown-horizontal-line

Crozet Elementary School Site Improvements


Project Scope

New parent drop-off to separate bus and vehicle traffic and new vestibule.


Project Manager: N. Craft Construction Start Date: June 2010
Design Firm: Heyward Boyd Architects Completion Date: December 2010
General Contractor: R. E. Lee and Son, Inc. Project Budget: $440,000

 

 

Crozet Elementary School


 
 
 
Contact the Department
Project Management Division
401 McIntire Road
Room 420
Charlottesville, VA 22902
434-872-4501
FAX: 434-293-0294
Email the Department