 Progress made in May

  • Stone veneer to near complete
  • Front canopy to near complete
  • Windows installed
  • Drywall and prime paint near complete
  • Ceiling grid near complete
  • Propane tanks installed
  • Rough grading for parking lot done
  • Transformer and electric service near complete
  • Coordinated electronic systems and cabling
  Anticipated in June
  • Complete Dominion power connection
  • Start-up HVAC units
  • Complete parking lot
  • Complete sidewalk steps and ramp (switchback)
  • VDOT acceptance of ADA sidewalk
  • Move Century Link fiber in Crozet Ave (conflicts with storm sewer)


     