Community Development  |  Crozet Library Project Update - 4/5/13
brown-horizontal-line

4/5/13

 Progress made in March

  • Completed high roof
  • Installed east elevation brick
  • Substantial progress on ductwork and plumbing
  • Wall and bulkhead framing – nearing completion
  • Installed temporary windows
  • Received VDOT acceptance of responsibility for fiber conflict with storm sewer
  • Coordinated furniture and books procurement with JMRL
  Anticipated in April 
  • Complete Dominion power connection
  • Start-up HVAC units
  • Complete brick
  • Parking lot grading
  • Sidewalk ramp (switchback)
  • VDOT acceptance of ADA sidewalk
  • Authorize Century Link to move fiber (conflicts with storm sewer)