Community Development  |  Crozet Library Project Update - 3/1/13
brown-horizontal-line

3/1/13

 Progress made in February

  • Completed CMU exterior walls
  • Installed south elevation brick
  • North and South lower roofs installed
  • Set HVAC units
  • Installed parking lot stormwater utilities
  Anticipated in March 
  • Complete Dominion power connection
  • Complete high roof
  • Coordinate furniture and books procurement with JMRL
  • VDOT acceptance of ADA sidewalk
  • Resolve fiber conflict with storm sewer 