Community Development  |  Crozet Library Project Update - 12/5/12
brown-horizontal-line

12/5/12

 Progress made in November

  • Completed backfill of retaining wall 
  • Set steel on west end of 2nd level
  • Poured slab on deck above lease area
  • Installed column piers in slab on grade area
  • Started pre-cast sills and lintels installation
  • Some progress on Crozet Ave fiber conflict resolution
  Anticipated in December
  • Complete 2nd Level Steel
  • Pour slab on grade (2nd level)
  • Start brick and stone installation
  • Resolve fiber conflict with storm sewer
      
     

 

 

>> Back to Crozet Library Homepage