Community Development  |  Crozet Library Project Update - 11/2/12
brown-horizontal-line

11/2/12

 Progress made in October
  • First level slab on grade poured
  • Second level foundation walls poured
  • Waterproofing done
  • Backfill of retaining wall started (25% done)
  • Adjusted floor outlets for modified furnishings plan
  • Identified likely Crozet Avenue fiber conflict resolution
  Anticipated in November
  • Complete backfill of retaining wall
  • Pour slab on deck above lease area
  • Resolve fiber conflict with storm sewer
  • Install column piers in slab on grade area
     
     