Community Development  |  Crozet Library Project Update - 9/28/12
brown-horizontal-line

9/28/12

 Progress made in September
  • First level footings complete
  • First level masonry walls -- 85% complete
  • First level steel erected (and portion of second level)
  • Crozet Avenue waterline relocation completed
  • Discovered fiber conflict with storm sewer


     
  Anticipated in October
  • Pour second level foundation walls
  • Waterproofing below-grade walls
  • Backfill at retaining walls
  • Pour slab on deck above lease area
  • Pour slab on grade - first level
  • Resolve fiber conflict with storm sewer
  • Connect storm sewer (if fiber conflict resolved)
     

Crozet Library Construction Update

Crozet Library Construction Update

 Crozet Library Construction Update

Crozet Library Construction Update 