Community Development  |  Crozet Library Project Update - 8/31/12
brown-horizontal-line

8/31/12

 Progress made in August
  • 80% of first level footings installed
  • First level retaining wall installed
  • First level masonry walls started
  • Water service installed
 
 Anticipated in September
  • Crozet Ave utilities installation
  • Steel erection started
  • Continue masonry walls
  • First level floor slab installation
  • 2nd level footings installation